How can I remove the summary tasks from appearing when creating a custome
report using the Monthly Calendar Report Definition "template"?
 
A

andy

Jose,

What i have done before is to remove the summary line that is contained in
the bars..
If you need to use the summary data change the line type to a block - if
you dont need to show the summary legend in your print copy , put a *in front
of the description in the bar