D
Dave Pliskin, PMP
I would like to assign "an owner" to a task that is a group activity. I have
added a new text column which I named Owner. In a perfect world, this column
could be linked to the Resources Initial field to control the contents of the
text field.
Is there a way to do this in project 2003 (non server?)
Thank you in advance for your suggestions.
added a new text column which I named Owner. In a perfect world, this column
could be linked to the Resources Initial field to control the contents of the
text field.
Is there a way to do this in project 2003 (non server?)
Thank you in advance for your suggestions.