I have been given a project to outline on ms project and seeing as i
have never used it before, i have come along quite a way but i'm stuck
on a few things that i need help with:
1. If a task has a fixed duration, does that mean i would add a
'milestone' in there or is there another function to state this? i added
the milestones but now it looks funny with black diamonds everywhere and
no info!
2. In the resource field, if you have two members of staff working on
the task, on the chart it cos up as '200'% be default how can you edit
it so it says just '2'.
3.if i had 3 tasks say they were:
Task names: Duration:
order compnents 7days
order production equipment 14days
install production equipment 25 days
meeting 1 day
however, install production equipment must not start until 20 DAYS
AFTER order components has been Completed and 40 DAYS AFTER order
production equipment, how would i show this on my gantts chart how would
i add the extra days in? I tried using the 'lag' function and i got like
a 9mnth gap in between before the meeting, how can i reduce the gap
because it doent make sense!
Help would be much appreciated, thank you!!!!
I have been given a project to outline on ms project and seeing as i
have never used it before, i have come along quite a way but i'm stuck
on a few things that i need help with:
1. If a task has a fixed duration, does that mean i would add a
'milestone' in there or is there another function to state this? i added
the milestones but now it looks funny with black diamonds everywhere and
no info!
2. In the resource field, if you have two members of staff working on
the task, on the chart it cos up as '200'% be default how can you edit
it so it says just '2'.
3.if i had 3 tasks say they were:
Task names: Duration:
order compnents 7days
order production equipment 14days
install production equipment 25 days
meeting 1 day
however, install production equipment must not start until 20 DAYS
AFTER order components has been Completed and 40 DAYS AFTER order
production equipment, how would i show this on my gantts chart how would
i add the extra days in? I tried using the 'lag' function and i got like
a 9mnth gap in between before the meeting, how can i reduce the gap
because it doent make sense!
Help would be much appreciated, thank you!!!!