E
EmiW
Hi there,
I need some help and am hoping I can explain it well enough for someone to
provide some suggestions.
I have milestone B and task A. Task A must be completed, at least one day
before Task B ends. Task B ‘s dates can shift ( independent of, and not
driven by, A) which would cause Task A's end date to move accordingly.
I want to be able to
1) show that B is a successor to A and
2) if the date on B changes (not due to A, but to other issues) then the
date on A would automatically shift appropriately to maintain the “end by one
day before†relationship.
I have been able to set up to have the dates adjust automatically, using
either an FF or SF with -1 or -2 days and while that does adjust the dates
appropriately, B shows up in the predecessor column as a predecessor to A.
Is there any way to set this up so that the dates change automatically and
with A showing as a predecessor to B?
I'm new to project so I'm sure it's user error here.
Appreciate any help that can be provided.
I need some help and am hoping I can explain it well enough for someone to
provide some suggestions.
I have milestone B and task A. Task A must be completed, at least one day
before Task B ends. Task B ‘s dates can shift ( independent of, and not
driven by, A) which would cause Task A's end date to move accordingly.
I want to be able to
1) show that B is a successor to A and
2) if the date on B changes (not due to A, but to other issues) then the
date on A would automatically shift appropriately to maintain the “end by one
day before†relationship.
I have been able to set up to have the dates adjust automatically, using
either an FF or SF with -1 or -2 days and while that does adjust the dates
appropriately, B shows up in the predecessor column as a predecessor to A.
Is there any way to set this up so that the dates change automatically and
with A showing as a predecessor to B?
I'm new to project so I'm sure it's user error here.
Appreciate any help that can be provided.