J
Jon
I am having issues with regards to the Earned value management within
Microsoft project 2003
Basically I have a list of tasks such as;
Predecessor
1 Power wash hull
2 Submit itp duration 0
3 Remove sea grating duration 5 2fs+20d
4 Conduct powerwash duration 15 3
5 Replace sea grating duration 6 4
6 Close of job duration 0 5
I would like to assign a total cost of $20,000 to the parent task (power
wash hull) instead of each individual line item as it is a fixed cost quoted
job.
What I am experiencing now is after the first week, the submit itp has been
completed yet project is stating that my BCWS is $12,000 however it should be
$0 as no physical work has commenced.
Basically I want to assign fixed costs to the parent level and calculate EVM
regardless of how many child tasks there are.
Is there a change of configuration for this method to be used? Or does MS
Project not support this method? If it does how would i go about doing it?
Cheers
Jon
Microsoft project 2003
Basically I have a list of tasks such as;
Predecessor
1 Power wash hull
2 Submit itp duration 0
3 Remove sea grating duration 5 2fs+20d
4 Conduct powerwash duration 15 3
5 Replace sea grating duration 6 4
6 Close of job duration 0 5
I would like to assign a total cost of $20,000 to the parent task (power
wash hull) instead of each individual line item as it is a fixed cost quoted
job.
What I am experiencing now is after the first week, the submit itp has been
completed yet project is stating that my BCWS is $12,000 however it should be
$0 as no physical work has commenced.
Basically I want to assign fixed costs to the parent level and calculate EVM
regardless of how many child tasks there are.
Is there a change of configuration for this method to be used? Or does MS
Project not support this method? If it does how would i go about doing it?
Cheers
Jon