Say I have two tasks as follows:
1. Build racing car From: 02 Nov 2009 to 23 Jun 2010 By: Jim
2. Build speed boat From: 02 Nov 2009 to 01 Mar 2010 By: Fred
Fred also can build racing cars, so I'd like him to work 100% on task 2
to finish his speed boat, and then join Jim on Task 1 on 02 Mar 2010 to
help Jim finish the task.
Can someone please help me and tell me how to assign the resources like
this, in MSP2007?
Thanks