using 2003. I have tasks that use different recources at different
rates.
example
Task A - dur = 3 wks
Resource 1 - 1st wk is 10%, 2d wk is 10%, 3d wk is 0%
Resource 2 - 1st wk is 20%, 2d wk is 30%, 3d wk is 50%
Resource 3 - 1st wk is 20%, 2d wk is 30%, 3d wk is 30%
how do I allocate that?