Help with tracking a project budget

D

dstevens

I am new to projects and need some help with how to enter a budget in
days by task. Currently, I am using the WORK field. When I enter
usage and it is greater than the budget (WORK field) it automatically
changes my budget (WORK field) to equal actual usage. I need to
maintain the variance between the original budgeted days and actual
days used by task.
 
J

Jan De Messemaeker

Hi,

You have to save a baseline before entering actuals.
Tools, tracking, save baseline
The field Baseline Work now holds the original estimate until you might
decide to again save a baseline.
HTH
 