M
Meg
I posted this yesterday morning and no one responded - not
sure if I wasn't clear or its just that there is no
answer. Can someone help?
Here's my issue:
I'm a relative novice to MS Projet. I added a Status field
to the Gantt chart and depending on the %complete, it
either says "Future Task", "Complete" or "late". We moved
our launch date out, so I changed the finish dates for a
bunch of tasks to a future date, but the status field
still says "Late". What am I doing wrong.
sure if I wasn't clear or its just that there is no
answer. Can someone help?
Here's my issue:
I'm a relative novice to MS Projet. I added a Status field
to the Gantt chart and depending on the %complete, it
either says "Future Task", "Complete" or "late". We moved
our launch date out, so I changed the finish dates for a
bunch of tasks to a future date, but the status field
still says "Late". What am I doing wrong.