help

M

mareveli

Help! Is there someone who will take pity on me and give me an email address
so I don't have to bother this community with my stupid questions? Here's
the deal...I've had to throw this schedule together really fast without time
to bone up on msproject. I loaded the resources incorrectly, a lot of the
durations are bogus because we wanted certain end dates to show. I just need
to be able to show accurate progress but really can't figure out which
approach is best for this when the data being used is not accurate. I am
taking a class, but not until next week and I really need to talk to someone
about the best way to move forward with this schedule. This project is
nearing its end and the customer was angry because there was no schedule, so
I've had to go back and enter work that has already been done. It was all
very rushed and the person I was getting the task etc. info from was in the
middle of moving from one house to another with his family and I had to keep
calling him on the phone... I try to get the answers from project help.
Sometimes I find the answers and sometimes I don't. Sometimes, I just can't
follow it. I've also found a wealth of info in this discussion group, but I
learn much faster by doing than by reading and I just don't have a lot of
time to put into it. So...if anyone is feeling merciful and can give me some
help, I would really appreciate it. My email address is (e-mail address removed).

Desperately yours,

Mareveli
 
J

John

mareveli said:
Help! Is there someone who will take pity on me and give me an email address
so I don't have to bother this community with my stupid questions? Here's
the deal...I've had to throw this schedule together really fast without time
to bone up on msproject. I loaded the resources incorrectly, a lot of the
durations are bogus because we wanted certain end dates to show. I just need
to be able to show accurate progress but really can't figure out which
approach is best for this when the data being used is not accurate. I am
taking a class, but not until next week and I really need to talk to someone
about the best way to move forward with this schedule. This project is
nearing its end and the customer was angry because there was no schedule, so
I've had to go back and enter work that has already been done. It was all
very rushed and the person I was getting the task etc. info from was in the
middle of moving from one house to another with his family and I had to keep
calling him on the phone... I try to get the answers from project help.
Sometimes I find the answers and sometimes I don't. Sometimes, I just can't
follow it. I've also found a wealth of info in this discussion group, but I
learn much faster by doing than by reading and I just don't have a lot of
time to put into it. So...if anyone is feeling merciful and can give me some
help, I would really appreciate it. My email address is (e-mail address removed).

Desperately yours,

Mareveli

Mareveli,
First of all, questions posted to this newsgroup, especially by new
users, are rarely stupid. Second, the sole purpose of this newsgroup is
to help Project users. The topics discussed here are generally of
interest to a wide audience and therefore it is desirable to keep the
discussion in the newsgroup. On rare occasions it may make sense to help
a user on a one-on-one basis, but so far, your issues don't appear to
fall into that category.

It appears you have been put between a rock and a hard place but you
certainly can NOT get "accurate progress" from a schedule plan that is
"bogus". The two just don't mix. If your customer is angry, (and he
probably should be if the project is nearing completion and there hasn't
been a valid plan all along), that's unfortunate. Where were the
stakeholders when the contract was let? Your company's management is
derelict for not having a valid plan developed and the customer is
derelict for not insisting that one be developed before the project
started.

OK, enough of the lecture. So what do you do now. Answer these questions
for yourself.
1. What benefit do we hope to gain by developing a plan after the fact,
especially a plan that is bogus to start with?
2. Since the project is near the end will the effort invested in a plan
now be worth the cost to develop/fix it?
3. Is the project severely over budget or late (a plan now won't fix
that)?
4. How has the project been managed up until now (find the management
processes that did work and stick with them - learn from those that
didn't)

It may well be that the best approach you can take at this point is to
make a list of items on both sides of question 4, including accurate
cost history for all phases of the project. These will be invaluable for
planning future projects. Next time you can do it with a good plan in
the beginning.

If you have specific questions please feel free to post them (you have
in previous posts), but I seriously doubt anyone is going to jump in and
volunteer to rescue you, your company and your customer from a failed
process, but then, I might be wrong.

I know this isn't the answer you want but this experience might just be
the best learning experience you will ever get with regard to managing a
project.

By the way, you may want to share this response with your management and
your customer - there's no reason for you to take the full "hit".

John
Project MVP
 
M

mareveli

wow...this is precisely why I wanted to take this off-line, so I could
hopefully avoid you John. Your sanctimonious reply is not in the least bit
helpful, but only rubs salt in an already painful wound. First of all...I
have just inherited this project and you have no clue how I, my company, or
the customer have arrived at this point. So please refrain from the
judgements and ciriticisms. If you don't want to help then don't. The
schedule needs to be there and I would like to show % complete based on what
I am being told by the experts is the percentage complete on the individual
tasks. I would like the real% complete to be reflected in the summary tasks
and the project summary. If someone knows how I can do this I would
appreciate the tip so I can just make it through the end of this project and
then I can start the right way with the next.

Hoping for a helpful response!

mareveli
 
M

Mike Glen

Hi Mareveli ,

I think John gave you a realistic and honest answer to your situation. :)

If you enter the %Complete for each individual task, then the Summary and
Project %Complete will be calculated for you, you have no control over this
and cannot fudge the summary figures without fudging the task's data. If
that's not happening, tell us what is happening, how/where you enter the
data and what you are expecting to see.

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for Project Tutorials

wrote:
 
M

mareveli

Well, maybe at this point I should just create a notes column, input the %s,
and title it "% complete." It is accurate data. The only problem with this
is that I am already using the notes column for notes.

mareveli
 
J

JulieS

Hi Mareveli,

You could use one of the Text fields (Text1 through Text30) for this
purpose if you are already using the Notes field.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
 
S

Steve House

Why can't you use the tracking tools that Project provides? Just remember
that "% Complete" refers to duration, not work performed and not the amount
of the deliverable that has been done. If a task has 5 days duration and
has been worked on for 3 days with 2 still to go, the task is 60% Complete.
If you have a task showing it starts such and such a date and a certain
duration and enter a number for % Complete, Project will assume it began on
the date the schedule shows and your input percentage of the total duration
has been consumed doing the task so far. Or regardless on the estimated
start date your schedule called for and the duration it shows, if you
display the Tracking Table in the Gantt chart view and enter the date the
task actually began in the Actual Start field, the amount of time that work
occupied so far in the Actual Duration column, and the resource's best guess
as to the amount of time remaining until the task is finished in the
Remaining Duration, Project will update the duration and display the correct
% Complete for you. And it will rollup those values to the summary task
lines and the Project Summary task as well, displaying there a weighted
average progress based on the actual progress posted for the activities.
Project IS showing you the real % complete in the summary lines - why do you
think it's not?
 
A

aaren

One more suggestion - am not sure how useful it is though. Why not use
Excel spreadsheet instead of MS Project - since most of the tasks are
complete. This spreadsheet could have the required columns and then
they can be filled out. Looking at the situation, am not too sure
whether putting everything together in MS Project is the way to go - it
looks like there will be too much of effort without corresponding
benefits.

HTH.


Steve said:
Why can't you use the tracking tools that Project provides? Just remember
that "% Complete" refers to duration, not work performed and not the amount
of the deliverable that has been done. If a task has 5 days duration and
has been worked on for 3 days with 2 still to go, the task is 60% Complete.
If you have a task showing it starts such and such a date and a certain
duration and enter a number for % Complete, Project will assume it began on
the date the schedule shows and your input percentage of the total duration
has been consumed doing the task so far. Or regardless on the estimated
start date your schedule called for and the duration it shows, if you
display the Tracking Table in the Gantt chart view and enter the date the
task actually began in the Actual Start field, the amount of time that work
occupied so far in the Actual Duration column, and the resource's best guess
as to the amount of time remaining until the task is finished in the
Remaining Duration, Project will update the duration and display the correct
% Complete for you. And it will rollup those values to the summary task
lines and the Project Summary task as well, displaying there a weighted
average progress based on the actual progress posted for the activities.
Project IS showing you the real % complete in the summary lines - why do you
think it's not?

--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs


mareveli said:
Well, maybe at this point I should just create a notes column, input the
%s,
and title it "% complete." It is accurate data. The only problem with
this
is that I am already using the notes column for notes.

mareveli
 
M

Mareveli

Thanks for all of the responses. I finally have some breathing space since I
don't have any deadlines for the next few days (I hope), so I should be able
to take the time now to obtain accurate dates and durations. If not, I'll
try Julie's suggestion.

Thanks again for the input!

Mareveli

aaren said:
One more suggestion - am not sure how useful it is though. Why not use
Excel spreadsheet instead of MS Project - since most of the tasks are
complete. This spreadsheet could have the required columns and then
they can be filled out. Looking at the situation, am not too sure
whether putting everything together in MS Project is the way to go - it
looks like there will be too much of effort without corresponding
benefits.

HTH.


Steve said:
Why can't you use the tracking tools that Project provides? Just remember
that "% Complete" refers to duration, not work performed and not the amount
of the deliverable that has been done. If a task has 5 days duration and
has been worked on for 3 days with 2 still to go, the task is 60% Complete.
If you have a task showing it starts such and such a date and a certain
duration and enter a number for % Complete, Project will assume it began on
the date the schedule shows and your input percentage of the total duration
has been consumed doing the task so far. Or regardless on the estimated
start date your schedule called for and the duration it shows, if you
display the Tracking Table in the Gantt chart view and enter the date the
task actually began in the Actual Start field, the amount of time that work
occupied so far in the Actual Duration column, and the resource's best guess
as to the amount of time remaining until the task is finished in the
Remaining Duration, Project will update the duration and display the correct
% Complete for you. And it will rollup those values to the summary task
lines and the Project Summary task as well, displaying there a weighted
average progress based on the actual progress posted for the activities.
Project IS showing you the real % complete in the summary lines - why do you
think it's not?

--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs


mareveli said:
Well, maybe at this point I should just create a notes column, input the
%s,
and title it "% complete." It is accurate data. The only problem with
this
is that I am already using the notes column for notes.

mareveli

:

Hi Mareveli ,

I think John gave you a realistic and honest answer to your situation. :)

If you enter the %Complete for each individual task, then the Summary and
Project %Complete will be calculated for you, you have no control over
this
and cannot fudge the summary figures without fudging the task's data. If
that's not happening, tell us what is happening, how/where you enter the
data and what you are expecting to see.

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for Project Tutorials

wrote:
wow...this is precisely why I wanted to take this off-line, so I could
hopefully avoid you John. Your sanctimonious reply is not in the
least bit helpful, but only rubs salt in an already painful wound.
First of all...I have just inherited this project and you have no
clue how I, my company, or the customer have arrived at this point.
So please refrain from the judgements and ciriticisms. If you don't
want to help then don't. The schedule needs to be there and I would
like to show % complete based on what I am being told by the experts
is the percentage complete on the individual tasks. I would like the
real% complete to be reflected in the summary tasks and the project
summary. If someone knows how I can do this I would appreciate the
tip so I can just make it through the end of this project and then I
can start the right way with the next.

Hoping for a helpful response!

mareveli

:

Help! Is there someone who will take pity on me and give me an
email address so I don't have to bother this community with my
stupid questions? Here's the deal...I've had to throw this
schedule together really fast without time to bone up on msproject.
I loaded the resources incorrectly, a lot of the durations are
bogus because we wanted certain end dates to show. I just need to
be able to show accurate progress but really can't figure out which
approach is best for this when the data being used is not accurate.
I am taking a class, but not until next week and I really need to
talk to someone about the best way to move forward with this
schedule. This project is nearing its end and the customer was
angry because there was no schedule, so I've had to go back and
enter work that has already been done. It was all very rushed and
the person I was getting the task etc. info from was in the middle
of moving from one house to another with his family and I had to
keep calling him on the phone... I try to get the answers from
project help. Sometimes I find the answers and sometimes I don't.
Sometimes, I just can't follow it. I've also found a wealth of
info in this discussion group, but I learn much faster by doing
than by reading and I just don't have a lot of time to put into it.
So...if anyone is feeling merciful and can give me some help, I
would really appreciate it. My email address is (e-mail address removed).

Desperately yours,

Mareveli

Mareveli,
First of all, questions posted to this newsgroup, especially by new
users, are rarely stupid. Second, the sole purpose of this newsgroup
is to help Project users. The topics discussed here are generally of
interest to a wide audience and therefore it is desirable to keep the
discussion in the newsgroup. On rare occasions it may make sense to
help a user on a one-on-one basis, but so far, your issues don't
appear to fall into that category.

It appears you have been put between a rock and a hard place but you
certainly can NOT get "accurate progress" from a schedule plan that
is "bogus". The two just don't mix. If your customer is angry, (and
he probably should be if the project is nearing completion and there
hasn't been a valid plan all along), that's unfortunate. Where were
the stakeholders when the contract was let? Your company's
management is derelict for not having a valid plan developed and the
customer is derelict for not insisting that one be developed before
the project started.

OK, enough of the lecture. So what do you do now. Answer these
questions for yourself.
1. What benefit do we hope to gain by developing a plan after the
fact, especially a plan that is bogus to start with?
2. Since the project is near the end will the effort invested in a
plan now be worth the cost to develop/fix it?
3. Is the project severely over budget or late (a plan now won't fix
that)?
4. How has the project been managed up until now (find the management
processes that did work and stick with them - learn from those that
didn't)

It may well be that the best approach you can take at this point is
to make a list of items on both sides of question 4, including
accurate cost history for all phases of the project. These will be
invaluable for planning future projects. Next time you can do it
with a good plan in the beginning.

If you have specific questions please feel free to post them (you
have in previous posts), but I seriously doubt anyone is going to
jump in and volunteer to rescue you, your company and your customer
from a failed process, but then, I might be wrong.

I know this isn't the answer you want but this experience might just
be the best learning experience you will ever get with regard to
managing a project.

By the way, you may want to share this response with your management
and your customer - there's no reason for you to take the full "hit".

John
Project MVP
 
S

Steve House

Sometimes a viable approach is to build the complete plan as if work had not
yet taken place using the durations that the tasks that are complete
actually took and the duration estimates for the tasks that are still to be
worked. Then switch to the tracking table and tracking Gantt views, mark
the completed tasks as done and where necessary update the Actual Start and
Actual Finish dates for them, then enter Actual Start dates and Actual and
updated Remaining durations (if necessary) for tasks that are in progress.
--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs


Mareveli said:
Thanks for all of the responses. I finally have some breathing space
since I
don't have any deadlines for the next few days (I hope), so I should be
able
to take the time now to obtain accurate dates and durations. If not,
I'll
try Julie's suggestion.

Thanks again for the input!

Mareveli

aaren said:
One more suggestion - am not sure how useful it is though. Why not use
Excel spreadsheet instead of MS Project - since most of the tasks are
complete. This spreadsheet could have the required columns and then
they can be filled out. Looking at the situation, am not too sure
whether putting everything together in MS Project is the way to go - it
looks like there will be too much of effort without corresponding
benefits.

HTH.


Steve said:
Why can't you use the tracking tools that Project provides? Just
remember
that "% Complete" refers to duration, not work performed and not the
amount
of the deliverable that has been done. If a task has 5 days duration
and
has been worked on for 3 days with 2 still to go, the task is 60%
Complete.
If you have a task showing it starts such and such a date and a certain
duration and enter a number for % Complete, Project will assume it
began on
the date the schedule shows and your input percentage of the total
duration
has been consumed doing the task so far. Or regardless on the
estimated
start date your schedule called for and the duration it shows, if you
display the Tracking Table in the Gantt chart view and enter the date
the
task actually began in the Actual Start field, the amount of time that
work
occupied so far in the Actual Duration column, and the resource's best
guess
as to the amount of time remaining until the task is finished in the
Remaining Duration, Project will update the duration and display the
correct
% Complete for you. And it will rollup those values to the summary
task
lines and the Project Summary task as well, displaying there a weighted
average progress based on the actual progress posted for the
activities.
Project IS showing you the real % complete in the summary lines - why
do you
think it's not?

--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs


Well, maybe at this point I should just create a notes column, input
the
%s,
and title it "% complete." It is accurate data. The only problem
with
this
is that I am already using the notes column for notes.

mareveli

:

Hi Mareveli ,

I think John gave you a realistic and honest answer to your
situation. :)

If you enter the %Complete for each individual task, then the
Summary and
Project %Complete will be calculated for you, you have no control
over
this
and cannot fudge the summary figures without fudging the task's
data. If
that's not happening, tell us what is happening, how/where you enter
the
data and what you are expecting to see.

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for Project Tutorials

wrote:
wow...this is precisely why I wanted to take this off-line, so I
could
hopefully avoid you John. Your sanctimonious reply is not in the
least bit helpful, but only rubs salt in an already painful wound.
First of all...I have just inherited this project and you have no
clue how I, my company, or the customer have arrived at this
point.
So please refrain from the judgements and ciriticisms. If you
don't
want to help then don't. The schedule needs to be there and I
would
like to show % complete based on what I am being told by the
experts
is the percentage complete on the individual tasks. I would like
the
real% complete to be reflected in the summary tasks and the
project
summary. If someone knows how I can do this I would appreciate
the
tip so I can just make it through the end of this project and then
I
can start the right way with the next.

Hoping for a helpful response!

mareveli

:

Help! Is there someone who will take pity on me and give me an
email address so I don't have to bother this community with my
stupid questions? Here's the deal...I've had to throw this
schedule together really fast without time to bone up on
msproject.
I loaded the resources incorrectly, a lot of the durations are
bogus because we wanted certain end dates to show. I just need
to
be able to show accurate progress but really can't figure out
which
approach is best for this when the data being used is not
accurate.
I am taking a class, but not until next week and I really need
to
talk to someone about the best way to move forward with this
schedule. This project is nearing its end and the customer was
angry because there was no schedule, so I've had to go back and
enter work that has already been done. It was all very rushed
and
the person I was getting the task etc. info from was in the
middle
of moving from one house to another with his family and I had to
keep calling him on the phone... I try to get the answers from
project help. Sometimes I find the answers and sometimes I
don't.
Sometimes, I just can't follow it. I've also found a wealth of
info in this discussion group, but I learn much faster by doing
than by reading and I just don't have a lot of time to put into
it.
So...if anyone is feeling merciful and can give me some help, I
would really appreciate it. My email address is
(e-mail address removed).

Desperately yours,

Mareveli

Mareveli,
First of all, questions posted to this newsgroup, especially by
new
users, are rarely stupid. Second, the sole purpose of this
newsgroup
is to help Project users. The topics discussed here are generally
of
interest to a wide audience and therefore it is desirable to keep
the
discussion in the newsgroup. On rare occasions it may make sense
to
help a user on a one-on-one basis, but so far, your issues don't
appear to fall into that category.

It appears you have been put between a rock and a hard place but
you
certainly can NOT get "accurate progress" from a schedule plan
that
is "bogus". The two just don't mix. If your customer is angry,
(and
he probably should be if the project is nearing completion and
there
hasn't been a valid plan all along), that's unfortunate. Where
were
the stakeholders when the contract was let? Your company's
management is derelict for not having a valid plan developed and
the
customer is derelict for not insisting that one be developed
before
the project started.

OK, enough of the lecture. So what do you do now. Answer these
questions for yourself.
1. What benefit do we hope to gain by developing a plan after the
fact, especially a plan that is bogus to start with?
2. Since the project is near the end will the effort invested in
a
plan now be worth the cost to develop/fix it?
3. Is the project severely over budget or late (a plan now won't
fix
that)?
4. How has the project been managed up until now (find the
management
processes that did work and stick with them - learn from those
that
didn't)

It may well be that the best approach you can take at this point
is
to make a list of items on both sides of question 4, including
accurate cost history for all phases of the project. These will
be
invaluable for planning future projects. Next time you can do it
with a good plan in the beginning.

If you have specific questions please feel free to post them (you
have in previous posts), but I seriously doubt anyone is going to
jump in and volunteer to rescue you, your company and your
customer
from a failed process, but then, I might be wrong.

I know this isn't the answer you want but this experience might
just
be the best learning experience you will ever get with regard to
managing a project.

By the way, you may want to share this response with your
management
and your customer - there's no reason for you to take the full
"hit".

John
Project MVP
 
M

Mareveli

Thanks Steve...I think I'm there. I've done all that now. What is
concerning me is that based on our billing and progress kept by the
engineering manager (who was doing all this through excel before the customer
demanded msproject) the progress is not quite 70%. The %complete I am
showing in msproject is 91%. I took all the data for the msproject schedule
from the eng mgrs spreadsheets. The % work complete is showing at 79%. It
seems that this is a much better calculation to show progress than %
complete. It's closer, but still off.

Mareveli

Steve House said:
Sometimes a viable approach is to build the complete plan as if work had not
yet taken place using the durations that the tasks that are complete
actually took and the duration estimates for the tasks that are still to be
worked. Then switch to the tracking table and tracking Gantt views, mark
the completed tasks as done and where necessary update the Actual Start and
Actual Finish dates for them, then enter Actual Start dates and Actual and
updated Remaining durations (if necessary) for tasks that are in progress.
--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs


Mareveli said:
Thanks for all of the responses. I finally have some breathing space
since I
don't have any deadlines for the next few days (I hope), so I should be
able
to take the time now to obtain accurate dates and durations. If not,
I'll
try Julie's suggestion.

Thanks again for the input!

Mareveli

aaren said:
One more suggestion - am not sure how useful it is though. Why not use
Excel spreadsheet instead of MS Project - since most of the tasks are
complete. This spreadsheet could have the required columns and then
they can be filled out. Looking at the situation, am not too sure
whether putting everything together in MS Project is the way to go - it
looks like there will be too much of effort without corresponding
benefits.

HTH.


Steve House wrote:
Why can't you use the tracking tools that Project provides? Just
remember
that "% Complete" refers to duration, not work performed and not the
amount
of the deliverable that has been done. If a task has 5 days duration
and
has been worked on for 3 days with 2 still to go, the task is 60%
Complete.
If you have a task showing it starts such and such a date and a certain
duration and enter a number for % Complete, Project will assume it
began on
the date the schedule shows and your input percentage of the total
duration
has been consumed doing the task so far. Or regardless on the
estimated
start date your schedule called for and the duration it shows, if you
display the Tracking Table in the Gantt chart view and enter the date
the
task actually began in the Actual Start field, the amount of time that
work
occupied so far in the Actual Duration column, and the resource's best
guess
as to the amount of time remaining until the task is finished in the
Remaining Duration, Project will update the duration and display the
correct
% Complete for you. And it will rollup those values to the summary
task
lines and the Project Summary task as well, displaying there a weighted
average progress based on the actual progress posted for the
activities.
Project IS showing you the real % complete in the summary lines - why
do you
think it's not?

--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs


Well, maybe at this point I should just create a notes column, input
the
%s,
and title it "% complete." It is accurate data. The only problem
with
this
is that I am already using the notes column for notes.

mareveli

:

Hi Mareveli ,

I think John gave you a realistic and honest answer to your
situation. :)

If you enter the %Complete for each individual task, then the
Summary and
Project %Complete will be calculated for you, you have no control
over
this
and cannot fudge the summary figures without fudging the task's
data. If
that's not happening, tell us what is happening, how/where you enter
the
data and what you are expecting to see.

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for Project Tutorials

wrote:
wow...this is precisely why I wanted to take this off-line, so I
could
hopefully avoid you John. Your sanctimonious reply is not in the
least bit helpful, but only rubs salt in an already painful wound.
First of all...I have just inherited this project and you have no
clue how I, my company, or the customer have arrived at this
point.
So please refrain from the judgements and ciriticisms. If you
don't
want to help then don't. The schedule needs to be there and I
would
like to show % complete based on what I am being told by the
experts
is the percentage complete on the individual tasks. I would like
the
real% complete to be reflected in the summary tasks and the
project
summary. If someone knows how I can do this I would appreciate
the
tip so I can just make it through the end of this project and then
I
can start the right way with the next.

Hoping for a helpful response!

mareveli

:

Help! Is there someone who will take pity on me and give me an
email address so I don't have to bother this community with my
stupid questions? Here's the deal...I've had to throw this
schedule together really fast without time to bone up on
msproject.
I loaded the resources incorrectly, a lot of the durations are
bogus because we wanted certain end dates to show. I just need
to
be able to show accurate progress but really can't figure out
which
approach is best for this when the data being used is not
accurate.
I am taking a class, but not until next week and I really need
to
talk to someone about the best way to move forward with this
schedule. This project is nearing its end and the customer was
angry because there was no schedule, so I've had to go back and
enter work that has already been done. It was all very rushed
and
the person I was getting the task etc. info from was in the
middle
of moving from one house to another with his family and I had to
keep calling him on the phone... I try to get the answers from
project help. Sometimes I find the answers and sometimes I
don't.
Sometimes, I just can't follow it. I've also found a wealth of
info in this discussion group, but I learn much faster by doing
than by reading and I just don't have a lot of time to put into
it.
So...if anyone is feeling merciful and can give me some help, I
would really appreciate it. My email address is
(e-mail address removed).

Desperately yours,

Mareveli

Mareveli,
First of all, questions posted to this newsgroup, especially by
new
users, are rarely stupid. Second, the sole purpose of this
newsgroup
is to help Project users. The topics discussed here are generally
of
interest to a wide audience and therefore it is desirable to keep
the
discussion in the newsgroup. On rare occasions it may make sense
to
help a user on a one-on-one basis, but so far, your issues don't
appear to fall into that category.

It appears you have been put between a rock and a hard place but
you
certainly can NOT get "accurate progress" from a schedule plan
that
is "bogus". The two just don't mix. If your customer is angry,
(and
he probably should be if the project is nearing completion and
there
hasn't been a valid plan all along), that's unfortunate. Where
were
the stakeholders when the contract was let? Your company's
management is derelict for not having a valid plan developed and
the
customer is derelict for not insisting that one be developed
before
the project started.

OK, enough of the lecture. So what do you do now. Answer these
questions for yourself.
1. What benefit do we hope to gain by developing a plan after the
fact, especially a plan that is bogus to start with?
2. Since the project is near the end will the effort invested in
a
plan now be worth the cost to develop/fix it?
3. Is the project severely over budget or late (a plan now won't
fix
that)?
4. How has the project been managed up until now (find the
management
processes that did work and stick with them - learn from those
that
didn't)

It may well be that the best approach you can take at this point
is
to make a list of items on both sides of question 4, including
accurate cost history for all phases of the project. These will
be
invaluable for planning future projects. Next time you can do it
with a good plan in the beginning.

If you have specific questions please feel free to post them (you
have in previous posts), but I seriously doubt anyone is going to
jump in and volunteer to rescue you, your company and your
customer
from a failed process, but then, I might be wrong.

I know this isn't the answer you want but this experience might
just
be the best learning experience you will ever get with regard to
managing a project.

By the way, you may want to share this response with your
management
and your customer - there's no reason for you to take the full
"hit".

John
Project MVP
 
S

Steve House

Project has three completion metrics available. % Complete refers to
available working time elapsed so far versus total project duration. % Work
Complete is the number of man-hours spent versus the total man-hours
required. And finally, % Physical Complete is an estimate of the amount of
deliverable completed versus the amount required (often a very tricky thing
to quantify - what objectively measurable attribute would the statement "The
computer program I'm writing is 65% Physical Complete" be referring to?)
--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs


Mareveli said:
Thanks Steve...I think I'm there. I've done all that now. What is
concerning me is that based on our billing and progress kept by the
engineering manager (who was doing all this through excel before the
customer
demanded msproject) the progress is not quite 70%. The %complete I am
showing in msproject is 91%. I took all the data for the msproject
schedule
from the eng mgrs spreadsheets. The % work complete is showing at 79%.
It
seems that this is a much better calculation to show progress than %
complete. It's closer, but still off.

Mareveli

Steve House said:
Sometimes a viable approach is to build the complete plan as if work had
not
yet taken place using the durations that the tasks that are complete
actually took and the duration estimates for the tasks that are still to
be
worked. Then switch to the tracking table and tracking Gantt views, mark
the completed tasks as done and where necessary update the Actual Start
and
Actual Finish dates for them, then enter Actual Start dates and Actual
and
updated Remaining durations (if necessary) for tasks that are in
progress.
--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs


Mareveli said:
Thanks for all of the responses. I finally have some breathing space
since I
don't have any deadlines for the next few days (I hope), so I should be
able
to take the time now to obtain accurate dates and durations. If not,
I'll
try Julie's suggestion.

Thanks again for the input!

Mareveli

:

One more suggestion - am not sure how useful it is though. Why not
use
Excel spreadsheet instead of MS Project - since most of the tasks are
complete. This spreadsheet could have the required columns and then
they can be filled out. Looking at the situation, am not too sure
whether putting everything together in MS Project is the way to go -
it
looks like there will be too much of effort without corresponding
benefits.

HTH.


Steve House wrote:
Why can't you use the tracking tools that Project provides? Just
remember
that "% Complete" refers to duration, not work performed and not the
amount
of the deliverable that has been done. If a task has 5 days
duration
and
has been worked on for 3 days with 2 still to go, the task is 60%
Complete.
If you have a task showing it starts such and such a date and a
certain
duration and enter a number for % Complete, Project will assume it
began on
the date the schedule shows and your input percentage of the total
duration
has been consumed doing the task so far. Or regardless on the
estimated
start date your schedule called for and the duration it shows, if
you
display the Tracking Table in the Gantt chart view and enter the
date
the
task actually began in the Actual Start field, the amount of time
that
work
occupied so far in the Actual Duration column, and the resource's
best
guess
as to the amount of time remaining until the task is finished in the
Remaining Duration, Project will update the duration and display the
correct
% Complete for you. And it will rollup those values to the summary
task
lines and the Project Summary task as well, displaying there a
weighted
average progress based on the actual progress posted for the
activities.
Project IS showing you the real % complete in the summary lines -
why
do you
think it's not?

--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs


Well, maybe at this point I should just create a notes column,
input
the
%s,
and title it "% complete." It is accurate data. The only problem
with
this
is that I am already using the notes column for notes.

mareveli

:

Hi Mareveli ,

I think John gave you a realistic and honest answer to your
situation. :)

If you enter the %Complete for each individual task, then the
Summary and
Project %Complete will be calculated for you, you have no control
over
this
and cannot fudge the summary figures without fudging the task's
data. If
that's not happening, tell us what is happening, how/where you
enter
the
data and what you are expecting to see.

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for Project Tutorials

wrote:
wow...this is precisely why I wanted to take this off-line, so
I
could
hopefully avoid you John. Your sanctimonious reply is not in
the
least bit helpful, but only rubs salt in an already painful
wound.
First of all...I have just inherited this project and you have
no
clue how I, my company, or the customer have arrived at this
point.
So please refrain from the judgements and ciriticisms. If you
don't
want to help then don't. The schedule needs to be there and I
would
like to show % complete based on what I am being told by the
experts
is the percentage complete on the individual tasks. I would
like
the
real% complete to be reflected in the summary tasks and the
project
summary. If someone knows how I can do this I would appreciate
the
tip so I can just make it through the end of this project and
then
I
can start the right way with the next.

Hoping for a helpful response!

mareveli

:


Help! Is there someone who will take pity on me and give me
an
email address so I don't have to bother this community with
my
stupid questions? Here's the deal...I've had to throw this
schedule together really fast without time to bone up on
msproject.
I loaded the resources incorrectly, a lot of the durations
are
bogus because we wanted certain end dates to show. I just
need
to
be able to show accurate progress but really can't figure out
which
approach is best for this when the data being used is not
accurate.
I am taking a class, but not until next week and I really
need
to
talk to someone about the best way to move forward with this
schedule. This project is nearing its end and the customer
was
angry because there was no schedule, so I've had to go back
and
enter work that has already been done. It was all very
rushed
and
the person I was getting the task etc. info from was in the
middle
of moving from one house to another with his family and I had
to
keep calling him on the phone... I try to get the answers
from
project help. Sometimes I find the answers and sometimes I
don't.
Sometimes, I just can't follow it. I've also found a wealth
of
info in this discussion group, but I learn much faster by
doing
than by reading and I just don't have a lot of time to put
into
it.
So...if anyone is feeling merciful and can give me some help,
I
would really appreciate it. My email address is
(e-mail address removed).

Desperately yours,

Mareveli

Mareveli,
First of all, questions posted to this newsgroup, especially
by
new
users, are rarely stupid. Second, the sole purpose of this
newsgroup
is to help Project users. The topics discussed here are
generally
of
interest to a wide audience and therefore it is desirable to
keep
the
discussion in the newsgroup. On rare occasions it may make
sense
to
help a user on a one-on-one basis, but so far, your issues
don't
appear to fall into that category.

It appears you have been put between a rock and a hard place
but
you
certainly can NOT get "accurate progress" from a schedule plan
that
is "bogus". The two just don't mix. If your customer is angry,
(and
he probably should be if the project is nearing completion and
there
hasn't been a valid plan all along), that's unfortunate. Where
were
the stakeholders when the contract was let? Your company's
management is derelict for not having a valid plan developed
and
the
customer is derelict for not insisting that one be developed
before
the project started.

OK, enough of the lecture. So what do you do now. Answer these
questions for yourself.
1. What benefit do we hope to gain by developing a plan after
the
fact, especially a plan that is bogus to start with?
2. Since the project is near the end will the effort invested
in
a
plan now be worth the cost to develop/fix it?
3. Is the project severely over budget or late (a plan now
won't
fix
that)?
4. How has the project been managed up until now (find the
management
processes that did work and stick with them - learn from those
that
didn't)

It may well be that the best approach you can take at this
point
is
to make a list of items on both sides of question 4, including
accurate cost history for all phases of the project. These
will
be
invaluable for planning future projects. Next time you can do
it
with a good plan in the beginning.

If you have specific questions please feel free to post them
(you
have in previous posts), but I seriously doubt anyone is going
to
jump in and volunteer to rescue you, your company and your
customer
from a failed process, but then, I might be wrong.

I know this isn't the answer you want but this experience
might
just
be the best learning experience you will ever get with regard
to
managing a project.

By the way, you may want to share this response with your
management
and your customer - there's no reason for you to take the full
"hit".

John
Project MVP
 
M

Mareveli

Thanks for staying with me....I do get the difference between the three.

Another question..maybe I'm supposed to start another thread???

What is the best way to create a weekly report which shows:
weekly plan%, weekly actual%, weekly delta%, cumul. plan%, cum actual% & cum
delta%?

Thanks,
Mareveli

Steve House said:
Project has three completion metrics available. % Complete refers to
available working time elapsed so far versus total project duration. % Work
Complete is the number of man-hours spent versus the total man-hours
required. And finally, % Physical Complete is an estimate of the amount of
deliverable completed versus the amount required (often a very tricky thing
to quantify - what objectively measurable attribute would the statement "The
computer program I'm writing is 65% Physical Complete" be referring to?)
--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs


Mareveli said:
Thanks Steve...I think I'm there. I've done all that now. What is
concerning me is that based on our billing and progress kept by the
engineering manager (who was doing all this through excel before the
customer
demanded msproject) the progress is not quite 70%. The %complete I am
showing in msproject is 91%. I took all the data for the msproject
schedule
from the eng mgrs spreadsheets. The % work complete is showing at 79%.
It
seems that this is a much better calculation to show progress than %
complete. It's closer, but still off.

Mareveli

Steve House said:
Sometimes a viable approach is to build the complete plan as if work had
not
yet taken place using the durations that the tasks that are complete
actually took and the duration estimates for the tasks that are still to
be
worked. Then switch to the tracking table and tracking Gantt views, mark
the completed tasks as done and where necessary update the Actual Start
and
Actual Finish dates for them, then enter Actual Start dates and Actual
and
updated Remaining durations (if necessary) for tasks that are in
progress.
--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs


Thanks for all of the responses. I finally have some breathing space
since I
don't have any deadlines for the next few days (I hope), so I should be
able
to take the time now to obtain accurate dates and durations. If not,
I'll
try Julie's suggestion.

Thanks again for the input!

Mareveli

:

One more suggestion - am not sure how useful it is though. Why not
use
Excel spreadsheet instead of MS Project - since most of the tasks are
complete. This spreadsheet could have the required columns and then
they can be filled out. Looking at the situation, am not too sure
whether putting everything together in MS Project is the way to go -
it
looks like there will be too much of effort without corresponding
benefits.

HTH.


Steve House wrote:
Why can't you use the tracking tools that Project provides? Just
remember
that "% Complete" refers to duration, not work performed and not the
amount
of the deliverable that has been done. If a task has 5 days
duration
and
has been worked on for 3 days with 2 still to go, the task is 60%
Complete.
If you have a task showing it starts such and such a date and a
certain
duration and enter a number for % Complete, Project will assume it
began on
the date the schedule shows and your input percentage of the total
duration
has been consumed doing the task so far. Or regardless on the
estimated
start date your schedule called for and the duration it shows, if
you
display the Tracking Table in the Gantt chart view and enter the
date
the
task actually began in the Actual Start field, the amount of time
that
work
occupied so far in the Actual Duration column, and the resource's
best
guess
as to the amount of time remaining until the task is finished in the
Remaining Duration, Project will update the duration and display the
correct
% Complete for you. And it will rollup those values to the summary
task
lines and the Project Summary task as well, displaying there a
weighted
average progress based on the actual progress posted for the
activities.
Project IS showing you the real % complete in the summary lines -
why
do you
think it's not?

--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs


Well, maybe at this point I should just create a notes column,
input
the
%s,
and title it "% complete." It is accurate data. The only problem
with
this
is that I am already using the notes column for notes.

mareveli

:

Hi Mareveli ,

I think John gave you a realistic and honest answer to your
situation. :)

If you enter the %Complete for each individual task, then the
Summary and
Project %Complete will be calculated for you, you have no control
over
this
and cannot fudge the summary figures without fudging the task's
data. If
that's not happening, tell us what is happening, how/where you
enter
the
data and what you are expecting to see.

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for Project Tutorials

wrote:
wow...this is precisely why I wanted to take this off-line, so
I
could
hopefully avoid you John. Your sanctimonious reply is not in
the
least bit helpful, but only rubs salt in an already painful
wound.
First of all...I have just inherited this project and you have
no
clue how I, my company, or the customer have arrived at this
point.
So please refrain from the judgements and ciriticisms. If you
don't
want to help then don't. The schedule needs to be there and I
would
like to show % complete based on what I am being told by the
experts
is the percentage complete on the individual tasks. I would
like
the
real% complete to be reflected in the summary tasks and the
project
summary. If someone knows how I can do this I would appreciate
the
tip so I can just make it through the end of this project and
then
I
can start the right way with the next.

Hoping for a helpful response!

mareveli

:


Help! Is there someone who will take pity on me and give me
an
email address so I don't have to bother this community with
my
stupid questions? Here's the deal...I've had to throw this
schedule together really fast without time to bone up on
msproject.
I loaded the resources incorrectly, a lot of the durations
are
bogus because we wanted certain end dates to show. I just
need
to
be able to show accurate progress but really can't figure out
which
approach is best for this when the data being used is not
accurate.
I am taking a class, but not until next week and I really
need
to
talk to someone about the best way to move forward with this
schedule. This project is nearing its end and the customer
was
angry because there was no schedule, so I've had to go back
and
enter work that has already been done. It was all very
rushed
and
the person I was getting the task etc. info from was in the
middle
of moving from one house to another with his family and I had
to
keep calling him on the phone... I try to get the answers
from
project help. Sometimes I find the answers and sometimes I
don't.
Sometimes, I just can't follow it. I've also found a wealth
of
info in this discussion group, but I learn much faster by
doing
than by reading and I just don't have a lot of time to put
into
it.
So...if anyone is feeling merciful and can give me some help,
I
would really appreciate it. My email address is
(e-mail address removed).

Desperately yours,

Mareveli

Mareveli,
First of all, questions posted to this newsgroup, especially
by
new
users, are rarely stupid. Second, the sole purpose of this
newsgroup
is to help Project users. The topics discussed here are
generally
of
interest to a wide audience and therefore it is desirable to
keep
the
discussion in the newsgroup. On rare occasions it may make
sense
to
help a user on a one-on-one basis, but so far, your issues
don't
appear to fall into that category.

It appears you have been put between a rock and a hard place
but
you
certainly can NOT get "accurate progress" from a schedule plan
that
is "bogus". The two just don't mix. If your customer is angry,
(and
he probably should be if the project is nearing completion and
there
hasn't been a valid plan all along), that's unfortunate. Where
were
the stakeholders when the contract was let? Your company's
management is derelict for not having a valid plan developed
and
the
customer is derelict for not insisting that one be developed
before
the project started.

OK, enough of the lecture. So what do you do now. Answer these
questions for yourself.
1. What benefit do we hope to gain by developing a plan after
the
fact, especially a plan that is bogus to start with?
2. Since the project is near the end will the effort invested
in
a
 
R

Rob Schneider

Project doesn't compute those values (weekly numbers). You should
decide the algorithm for making those computations, assign the results
of those computations to custom number fields, display those fields on
the screen then print the screen.
Thanks for staying with me....I do get the difference between the three.

Another question..maybe I'm supposed to start another thread???

What is the best way to create a weekly report which shows:
weekly plan%, weekly actual%, weekly delta%, cumul. plan%, cum actual% & cum
delta%?

Thanks,
Mareveli

Steve House said:
Project has three completion metrics available. % Complete refers to
available working time elapsed so far versus total project duration. % Work
Complete is the number of man-hours spent versus the total man-hours
required. And finally, % Physical Complete is an estimate of the amount of
deliverable completed versus the amount required (often a very tricky thing
to quantify - what objectively measurable attribute would the statement "The
computer program I'm writing is 65% Physical Complete" be referring to?)
--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs


Mareveli said:
Thanks Steve...I think I'm there. I've done all that now. What is
concerning me is that based on our billing and progress kept by the
engineering manager (who was doing all this through excel before the
customer
demanded msproject) the progress is not quite 70%. The %complete I am
showing in msproject is 91%. I took all the data for the msproject
schedule
from the eng mgrs spreadsheets. The % work complete is showing at 79%.
It
seems that this is a much better calculation to show progress than %
complete. It's closer, but still off.

Mareveli

:

Sometimes a viable approach is to build the complete plan as if work had
not
yet taken place using the durations that the tasks that are complete
actually took and the duration estimates for the tasks that are still to
be
worked. Then switch to the tracking table and tracking Gantt views, mark
the completed tasks as done and where necessary update the Actual Start
and
Actual Finish dates for them, then enter Actual Start dates and Actual
and
updated Remaining durations (if necessary) for tasks that are in
progress.
--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs


Thanks for all of the responses. I finally have some breathing space
since I
don't have any deadlines for the next few days (I hope), so I should be
able
to take the time now to obtain accurate dates and durations. If not,
I'll
try Julie's suggestion.

Thanks again for the input!

Mareveli

:

One more suggestion - am not sure how useful it is though. Why not
use
Excel spreadsheet instead of MS Project - since most of the tasks are
complete. This spreadsheet could have the required columns and then
they can be filled out. Looking at the situation, am not too sure
whether putting everything together in MS Project is the way to go -
it
looks like there will be too much of effort without corresponding
benefits.

HTH.


Steve House wrote:
Why can't you use the tracking tools that Project provides? Just
remember
that "% Complete" refers to duration, not work performed and not the
amount
of the deliverable that has been done. If a task has 5 days
duration
and
has been worked on for 3 days with 2 still to go, the task is 60%
Complete.
If you have a task showing it starts such and such a date and a
certain
duration and enter a number for % Complete, Project will assume it
began on
the date the schedule shows and your input percentage of the total
duration
has been consumed doing the task so far. Or regardless on the
estimated
start date your schedule called for and the duration it shows, if
you
display the Tracking Table in the Gantt chart view and enter the
date
the
task actually began in the Actual Start field, the amount of time
that
work
occupied so far in the Actual Duration column, and the resource's
best
guess
as to the amount of time remaining until the task is finished in the
Remaining Duration, Project will update the duration and display the
correct
% Complete for you. And it will rollup those values to the summary
task
lines and the Project Summary task as well, displaying there a
weighted
average progress based on the actual progress posted for the
activities.
Project IS showing you the real % complete in the summary lines -
why
do you
think it's not?

--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs


Well, maybe at this point I should just create a notes column,
input
the
%s,
and title it "% complete." It is accurate data. The only problem
with
this
is that I am already using the notes column for notes.

mareveli

:

Hi Mareveli ,

I think John gave you a realistic and honest answer to your
situation. :)

If you enter the %Complete for each individual task, then the
Summary and
Project %Complete will be calculated for you, you have no control
over
this
and cannot fudge the summary figures without fudging the task's
data. If
that's not happening, tell us what is happening, how/where you
enter
the
data and what you are expecting to see.

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for Project Tutorials

wrote:
wow...this is precisely why I wanted to take this off-line, so
I
could
hopefully avoid you John. Your sanctimonious reply is not in
the
least bit helpful, but only rubs salt in an already painful
wound.
First of all...I have just inherited this project and you have
no
clue how I, my company, or the customer have arrived at this
point.
So please refrain from the judgements and ciriticisms. If you
don't
want to help then don't. The schedule needs to be there and I
would
like to show % complete based on what I am being told by the
experts
is the percentage complete on the individual tasks. I would
like
the
real% complete to be reflected in the summary tasks and the
project
summary. If someone knows how I can do this I would appreciate
the
tip so I can just make it through the end of this project and
then
I
can start the right way with the next.

Hoping for a helpful response!

mareveli

:


Help! Is there someone who will take pity on me and give me
an
email address so I don't have to bother this community with
my
stupid questions? Here's the deal...I've had to throw this
schedule together really fast without time to bone up on
msproject.
I loaded the resources incorrectly, a lot of the durations
are
bogus because we wanted certain end dates to show. I just
need
to
be able to show accurate progress but really can't figure out
which
approach is best for this when the data being used is not
accurate.
I am taking a class, but not until next week and I really
need
to
talk to someone about the best way to move forward with this
schedule. This project is nearing its end and the customer
was
angry because there was no schedule, so I've had to go back
and
enter work that has already been done. It was all very
rushed
and
the person I was getting the task etc. info from was in the
middle
of moving from one house to another with his family and I had
to
keep calling him on the phone... I try to get the answers
from
project help. Sometimes I find the answers and sometimes I
don't.
Sometimes, I just can't follow it. I've also found a wealth
of
info in this discussion group, but I learn much faster by
doing
than by reading and I just don't have a lot of time to put
into
it.
So...if anyone is feeling merciful and can give me some help,
I
would really appreciate it. My email address is
(e-mail address removed).

Desperately yours,

Mareveli
Mareveli,
First of all, questions posted to this newsgroup, especially
by
new
users, are rarely stupid. Second, the sole purpose of this
newsgroup
is to help Project users. The topics discussed here are
generally
of
interest to a wide audience and therefore it is desirable to
keep
the
discussion in the newsgroup. On rare occasions it may make
sense
to
help a user on a one-on-one basis, but so far, your issues
don't
appear to fall into that category.

It appears you have been put between a rock and a hard place
but
you
certainly can NOT get "accurate progress" from a schedule plan
that
is "bogus". The two just don't mix. If your customer is angry,
(and
he probably should be if the project is nearing completion and
there
hasn't been a valid plan all along), that's unfortunate. Where
were
the stakeholders when the contract was let? Your company's
management is derelict for not having a valid plan developed
and
the
customer is derelict for not insisting that one be developed
before
the project started.

OK, enough of the lecture. So what do you do now. Answer these
questions for yourself.
1. What benefit do we hope to gain by developing a plan after
the
fact, especially a plan that is bogus to start with?
2. Since the project is near the end will the effort invested
in
a
 
M

Mareveli

I don't necessarily need to see this in msproject. If I can import the data
into excel and view it there, that would be great. I'm surprised that there
isn't a way to see weekly progress, it seems like a very reasonable way to
monitor progress. Even a weekly view of work planned vs actual work in excel
would help.

Mareveli



Rob Schneider said:
Project doesn't compute those values (weekly numbers). You should
decide the algorithm for making those computations, assign the results
of those computations to custom number fields, display those fields on
the screen then print the screen.
Thanks for staying with me....I do get the difference between the three.

Another question..maybe I'm supposed to start another thread???

What is the best way to create a weekly report which shows:
weekly plan%, weekly actual%, weekly delta%, cumul. plan%, cum actual% & cum
delta%?

Thanks,
Mareveli

Steve House said:
Project has three completion metrics available. % Complete refers to
available working time elapsed so far versus total project duration. % Work
Complete is the number of man-hours spent versus the total man-hours
required. And finally, % Physical Complete is an estimate of the amount of
deliverable completed versus the amount required (often a very tricky thing
to quantify - what objectively measurable attribute would the statement "The
computer program I'm writing is 65% Physical Complete" be referring to?)
--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs


Thanks Steve...I think I'm there. I've done all that now. What is
concerning me is that based on our billing and progress kept by the
engineering manager (who was doing all this through excel before the
customer
demanded msproject) the progress is not quite 70%. The %complete I am
showing in msproject is 91%. I took all the data for the msproject
schedule
from the eng mgrs spreadsheets. The % work complete is showing at 79%.
It
seems that this is a much better calculation to show progress than %
complete. It's closer, but still off.

Mareveli

:

Sometimes a viable approach is to build the complete plan as if work had
not
yet taken place using the durations that the tasks that are complete
actually took and the duration estimates for the tasks that are still to
be
worked. Then switch to the tracking table and tracking Gantt views, mark
the completed tasks as done and where necessary update the Actual Start
and
Actual Finish dates for them, then enter Actual Start dates and Actual
and
updated Remaining durations (if necessary) for tasks that are in
progress.
--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs


Thanks for all of the responses. I finally have some breathing space
since I
don't have any deadlines for the next few days (I hope), so I should be
able
to take the time now to obtain accurate dates and durations. If not,
I'll
try Julie's suggestion.

Thanks again for the input!

Mareveli

:

One more suggestion - am not sure how useful it is though. Why not
use
Excel spreadsheet instead of MS Project - since most of the tasks are
complete. This spreadsheet could have the required columns and then
they can be filled out. Looking at the situation, am not too sure
whether putting everything together in MS Project is the way to go -
it
looks like there will be too much of effort without corresponding
benefits.

HTH.


Steve House wrote:
Why can't you use the tracking tools that Project provides? Just
remember
that "% Complete" refers to duration, not work performed and not the
amount
of the deliverable that has been done. If a task has 5 days
duration
and
has been worked on for 3 days with 2 still to go, the task is 60%
Complete.
If you have a task showing it starts such and such a date and a
certain
duration and enter a number for % Complete, Project will assume it
began on
the date the schedule shows and your input percentage of the total
duration
has been consumed doing the task so far. Or regardless on the
estimated
start date your schedule called for and the duration it shows, if
you
display the Tracking Table in the Gantt chart view and enter the
date
the
task actually began in the Actual Start field, the amount of time
that
work
occupied so far in the Actual Duration column, and the resource's
best
guess
as to the amount of time remaining until the task is finished in the
Remaining Duration, Project will update the duration and display the
correct
% Complete for you. And it will rollup those values to the summary
task
lines and the Project Summary task as well, displaying there a
weighted
average progress based on the actual progress posted for the
activities.
Project IS showing you the real % complete in the summary lines -
why
do you
think it's not?

--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs


Well, maybe at this point I should just create a notes column,
input
the
%s,
and title it "% complete." It is accurate data. The only problem
with
this
is that I am already using the notes column for notes.

mareveli

:

Hi Mareveli ,

I think John gave you a realistic and honest answer to your
situation. :)

If you enter the %Complete for each individual task, then the
Summary and
Project %Complete will be calculated for you, you have no control
over
this
and cannot fudge the summary figures without fudging the task's
data. If
that's not happening, tell us what is happening, how/where you
enter
the
data and what you are expecting to see.

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for Project Tutorials

wrote:
wow...this is precisely why I wanted to take this off-line, so
I
could
hopefully avoid you John. Your sanctimonious reply is not in
the
least bit helpful, but only rubs salt in an already painful
wound.
First of all...I have just inherited this project and you have
no
clue how I, my company, or the customer have arrived at this
point.
So please refrain from the judgements and ciriticisms. If you
don't
want to help then don't. The schedule needs to be there and I
would
like to show % complete based on what I am being told by the
experts
is the percentage complete on the individual tasks. I would
like
the
real% complete to be reflected in the summary tasks and the
project
summary. If someone knows how I can do this I would appreciate
the
tip so I can just make it through the end of this project and
then
I
can start the right way with the next.

Hoping for a helpful response!

mareveli

:


Help! Is there someone who will take pity on me and give me
an
email address so I don't have to bother this community with
my
stupid questions? Here's the deal...I've had to throw this
schedule together really fast without time to bone up on
msproject.
I loaded the resources incorrectly, a lot of the durations
are
bogus because we wanted certain end dates to show. I just
need
to
be able to show accurate progress but really can't figure out
which
approach is best for this when the data being used is not
accurate.
I am taking a class, but not until next week and I really
need
to
talk to someone about the best way to move forward with this
schedule. This project is nearing its end and the customer
was
angry because there was no schedule, so I've had to go back
and
enter work that has already been done. It was all very
rushed
and
the person I was getting the task etc. info from was in the
middle
of moving from one house to another with his family and I had
to
keep calling him on the phone... I try to get the answers
from
project help. Sometimes I find the answers and sometimes I
don't.
Sometimes, I just can't follow it. I've also found a wealth
of
info in this discussion group, but I learn much faster by
doing
than by reading and I just don't have a lot of time to put
into
it.
So...if anyone is feeling merciful and can give me some help,
I
would really appreciate it. My email address is
(e-mail address removed).

Desperately yours,

Mareveli
Mareveli,
First of all, questions posted to this newsgroup, especially
by
new
users, are rarely stupid. Second, the sole purpose of this
newsgroup
is to help Project users. The topics discussed here are
generally
of
interest to a wide audience and therefore it is desirable to
keep
the
discussion in the newsgroup. On rare occasions it may make
sense
to
help a user on a one-on-one basis, but so far, your issues
don't
appear to fall into that category.

It appears you have been put between a rock and a hard place
but
you
certainly can NOT get "accurate progress" from a schedule plan
that
is "bogus". The two just don't mix. If your customer is angry,
(and
he probably should be if the project is nearing completion and
there
 
J

John

Mareveli said:
I don't necessarily need to see this in msproject. If I can import the data
into excel and view it there, that would be great. I'm surprised that there
isn't a way to see weekly progress, it seems like a very reasonable way to
monitor progress. Even a weekly view of work planned vs actual work in excel
would help.

Mareveli

Mareveli,
As you found out from Steve's response, Project has three different ways
of measuring progress. One is based on duration, one is based on effort
(work) and the third is more-or-less user defined. Given that, as Rob
indicated in his response, it depends on how you define the various
progress parameters you listed (i.e. weekly plan %, weekly actual %,
etc.).

In the Project Management world, "progress" is measured using earned
value metrics, rather than basing everything on simple percent complete.
That's why you don't see fields in Project that relate directly to the
progress parameters you listed. If you are not familiar with earned
value, it basically measures progress by comparing cost and schedule to
a baseline. Earned value is computed in terms of dollars (or whatever
the local monetary type).

You can see the weekly percent complete (duration based) on the Task
Usage view if the timescale is set for weeks. And the cumulative actual
percent complete (again duration based) is the % Complete field itself.
However, no such parameter exists for weekly plan % complete, weekly
delta % complete, or cumulative plan % complete.

So, whether the custom parameters are calculated in Project or export to
another application, the exact formula needs to be defined.

Hope this helps.
John
Project MVP
Rob Schneider said:
Project doesn't compute those values (weekly numbers). You should
decide the algorithm for making those computations, assign the results
of those computations to custom number fields, display those fields on
the screen then print the screen.
Thanks for staying with me....I do get the difference between the three.

Another question..maybe I'm supposed to start another thread???

What is the best way to create a weekly report which shows:
weekly plan%, weekly actual%, weekly delta%, cumul. plan%, cum actual% &
cum
delta%?

Thanks,
Mareveli

:

Project has three completion metrics available. % Complete refers to
available working time elapsed so far versus total project duration. %
Work
Complete is the number of man-hours spent versus the total man-hours
required. And finally, % Physical Complete is an estimate of the amount
of
deliverable completed versus the amount required (often a very tricky
thing
to quantify - what objectively measurable attribute would the statement
"The
computer program I'm writing is 65% Physical Complete" be referring to?)
--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs


Thanks Steve...I think I'm there. I've done all that now. What is
concerning me is that based on our billing and progress kept by the
engineering manager (who was doing all this through excel before the
customer
demanded msproject) the progress is not quite 70%. The %complete I am
showing in msproject is 91%. I took all the data for the msproject
schedule
from the eng mgrs spreadsheets. The % work complete is showing at 79%.
It
seems that this is a much better calculation to show progress than %
complete. It's closer, but still off.

Mareveli

:

Sometimes a viable approach is to build the complete plan as if work
had
not
yet taken place using the durations that the tasks that are complete
actually took and the duration estimates for the tasks that are still
to
be
worked. Then switch to the tracking table and tracking Gantt views,
mark
the completed tasks as done and where necessary update the Actual
Start
and
Actual Finish dates for them, then enter Actual Start dates and Actual
and
updated Remaining durations (if necessary) for tasks that are in
progress.
--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs


Thanks for all of the responses. I finally have some breathing space
since I
don't have any deadlines for the next few days (I hope), so I should
be
able
to take the time now to obtain accurate dates and durations. If
not,
I'll
try Julie's suggestion.

Thanks again for the input!

Mareveli

:

One more suggestion - am not sure how useful it is though. Why not
use
Excel spreadsheet instead of MS Project - since most of the tasks
are
complete. This spreadsheet could have the required columns and then
they can be filled out. Looking at the situation, am not too sure
whether putting everything together in MS Project is the way to go -
it
looks like there will be too much of effort without corresponding
benefits.

HTH.


Steve House wrote:
Why can't you use the tracking tools that Project provides? Just
remember
that "% Complete" refers to duration, not work performed and not
the
amount
of the deliverable that has been done. If a task has 5 days
duration
and
has been worked on for 3 days with 2 still to go, the task is 60%
Complete.
If you have a task showing it starts such and such a date and a
certain
duration and enter a number for % Complete, Project will assume it
began on
the date the schedule shows and your input percentage of the total
duration
has been consumed doing the task so far. Or regardless on the
estimated
start date your schedule called for and the duration it shows, if
you
display the Tracking Table in the Gantt chart view and enter the
date
the
task actually began in the Actual Start field, the amount of time
that
work
occupied so far in the Actual Duration column, and the resource's
best
guess
as to the amount of time remaining until the task is finished in
the
Remaining Duration, Project will update the duration and display
the
correct
% Complete for you. And it will rollup those values to the summary
task
lines and the Project Summary task as well, displaying there a
weighted
average progress based on the actual progress posted for the
activities.
Project IS showing you the real % complete in the summary lines -
why
do you
think it's not?

--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs


Well, maybe at this point I should just create a notes column,
input
the
%s,
and title it "% complete." It is accurate data. The only problem
with
this
is that I am already using the notes column for notes.

mareveli

:

Hi Mareveli ,

I think John gave you a realistic and honest answer to your
situation. :)

If you enter the %Complete for each individual task, then the
Summary and
Project %Complete will be calculated for you, you have no control
over
this
and cannot fudge the summary figures without fudging the task's
data. If
that's not happening, tell us what is happening, how/where you
enter
the
data and what you are expecting to see.

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for Project Tutorials

wrote:
wow...this is precisely why I wanted to take this off-line, so
I
could
hopefully avoid you John. Your sanctimonious reply is not in
the
least bit helpful, but only rubs salt in an already painful
wound.
First of all...I have just inherited this project and you have
no
clue how I, my company, or the customer have arrived at this
point.
So please refrain from the judgements and ciriticisms. If you
don't
want to help then don't. The schedule needs to be there and I
would
like to show % complete based on what I am being told by the
experts
is the percentage complete on the individual tasks. I would
like
the
real% complete to be reflected in the summary tasks and the
project
summary. If someone knows how I can do this I would appreciate
the
tip so I can just make it through the end of this project and
then
I
can start the right way with the next.

Hoping for a helpful response!

mareveli

:


Help! Is there someone who will take pity on me and give me
an
email address so I don't have to bother this community with
my
stupid questions? Here's the deal...I've had to throw this
schedule together really fast without time to bone up on
msproject.
I loaded the resources incorrectly, a lot of the durations
are
bogus because we wanted certain end dates to show. I just
need
to
be able to show accurate progress but really can't figure out
which
approach is best for this when the data being used is not
accurate.
I am taking a class, but not until next week and I really
need
to
talk to someone about the best way to move forward with this
schedule. This project is nearing its end and the customer
was
angry because there was no schedule, so I've had to go back
and
enter work that has already been done. It was all very
rushed
and
the person I was getting the task etc. info from was in the
middle
of moving from one house to another with his family and I had
to
keep calling him on the phone... I try to get the answers
from
project help. Sometimes I find the answers and sometimes I
don't.
Sometimes, I just can't follow it. I've also found a wealth
of
info in this discussion group, but I learn much faster by
doing
than by reading and I just don't have a lot of time to put
into
it.
So...if anyone is feeling merciful and can give me some help,
I
would really appreciate it. My email address is
(e-mail address removed).

Desperately yours,

Mareveli
Mareveli,
First of all, questions posted to this newsgroup, especially
by
new
users, are rarely stupid. Second, the sole purpose of this
newsgroup
is to help Project users. The topics discussed here are
generally
of
interest to a wide audience and therefore it is desirable to
keep
the
discussion in the newsgroup. On rare occasions it may make
sense
to
help a user on a one-on-one basis, but so far, your issues
don't
appear to fall into that category.

It appears you have been put between a rock and a hard place
but
you
certainly can NOT get "accurate progress" from a schedule plan
that
is "bogus". The two just don't mix. If your customer is angry,
(and
he probably should be if the project is nearing completion and
there
 
M

Mareveli

It sounds like you are telling me that it can be done through a "custom
parameter" and that it can be defined in Project. Can you point me in the
right direction for how to do this?

Thank you and by the way...I apologize for my earlier response. I was
beyond stressed, but that was no excuse for such harshness.

Mareveli

John said:
Mareveli said:
I don't necessarily need to see this in msproject. If I can import the data
into excel and view it there, that would be great. I'm surprised that there
isn't a way to see weekly progress, it seems like a very reasonable way to
monitor progress. Even a weekly view of work planned vs actual work in excel
would help.

Mareveli

Mareveli,
As you found out from Steve's response, Project has three different ways
of measuring progress. One is based on duration, one is based on effort
(work) and the third is more-or-less user defined. Given that, as Rob
indicated in his response, it depends on how you define the various
progress parameters you listed (i.e. weekly plan %, weekly actual %,
etc.).

In the Project Management world, "progress" is measured using earned
value metrics, rather than basing everything on simple percent complete.
That's why you don't see fields in Project that relate directly to the
progress parameters you listed. If you are not familiar with earned
value, it basically measures progress by comparing cost and schedule to
a baseline. Earned value is computed in terms of dollars (or whatever
the local monetary type).

You can see the weekly percent complete (duration based) on the Task
Usage view if the timescale is set for weeks. And the cumulative actual
percent complete (again duration based) is the % Complete field itself.
However, no such parameter exists for weekly plan % complete, weekly
delta % complete, or cumulative plan % complete.

So, whether the custom parameters are calculated in Project or export to
another application, the exact formula needs to be defined.

Hope this helps.
John
Project MVP
Rob Schneider said:
Project doesn't compute those values (weekly numbers). You should
decide the algorithm for making those computations, assign the results
of those computations to custom number fields, display those fields on
the screen then print the screen.

Mareveli wrote:
Thanks for staying with me....I do get the difference between the three.

Another question..maybe I'm supposed to start another thread???

What is the best way to create a weekly report which shows:
weekly plan%, weekly actual%, weekly delta%, cumul. plan%, cum actual% &
cum
delta%?

Thanks,
Mareveli

:

Project has three completion metrics available. % Complete refers to
available working time elapsed so far versus total project duration. %
Work
Complete is the number of man-hours spent versus the total man-hours
required. And finally, % Physical Complete is an estimate of the amount
of
deliverable completed versus the amount required (often a very tricky
thing
to quantify - what objectively measurable attribute would the statement
"The
computer program I'm writing is 65% Physical Complete" be referring to?)
--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs


Thanks Steve...I think I'm there. I've done all that now. What is
concerning me is that based on our billing and progress kept by the
engineering manager (who was doing all this through excel before the
customer
demanded msproject) the progress is not quite 70%. The %complete I am
showing in msproject is 91%. I took all the data for the msproject
schedule
from the eng mgrs spreadsheets. The % work complete is showing at 79%.
It
seems that this is a much better calculation to show progress than %
complete. It's closer, but still off.

Mareveli

:

Sometimes a viable approach is to build the complete plan as if work
had
not
yet taken place using the durations that the tasks that are complete
actually took and the duration estimates for the tasks that are still
to
be
worked. Then switch to the tracking table and tracking Gantt views,
mark
the completed tasks as done and where necessary update the Actual
Start
and
Actual Finish dates for them, then enter Actual Start dates and Actual
and
updated Remaining durations (if necessary) for tasks that are in
progress.
--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs


Thanks for all of the responses. I finally have some breathing space
since I
don't have any deadlines for the next few days (I hope), so I should
be
able
to take the time now to obtain accurate dates and durations. If
not,
I'll
try Julie's suggestion.

Thanks again for the input!

Mareveli

:

One more suggestion - am not sure how useful it is though. Why not
use
Excel spreadsheet instead of MS Project - since most of the tasks
are
complete. This spreadsheet could have the required columns and then
they can be filled out. Looking at the situation, am not too sure
whether putting everything together in MS Project is the way to go -
it
looks like there will be too much of effort without corresponding
benefits.

HTH.


Steve House wrote:
Why can't you use the tracking tools that Project provides? Just
remember
that "% Complete" refers to duration, not work performed and not
the
amount
of the deliverable that has been done. If a task has 5 days
duration
and
has been worked on for 3 days with 2 still to go, the task is 60%
Complete.
If you have a task showing it starts such and such a date and a
certain
duration and enter a number for % Complete, Project will assume it
began on
the date the schedule shows and your input percentage of the total
duration
has been consumed doing the task so far. Or regardless on the
estimated
start date your schedule called for and the duration it shows, if
you
display the Tracking Table in the Gantt chart view and enter the
date
the
task actually began in the Actual Start field, the amount of time
that
work
occupied so far in the Actual Duration column, and the resource's
best
guess
as to the amount of time remaining until the task is finished in
the
Remaining Duration, Project will update the duration and display
the
correct
% Complete for you. And it will rollup those values to the summary
task
lines and the Project Summary task as well, displaying there a
weighted
average progress based on the actual progress posted for the
activities.
Project IS showing you the real % complete in the summary lines -
why
do you
think it's not?

--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs


Well, maybe at this point I should just create a notes column,
input
the
%s,
and title it "% complete." It is accurate data. The only problem
with
this
is that I am already using the notes column for notes.

mareveli

:

Hi Mareveli ,

I think John gave you a realistic and honest answer to your
situation. :)

If you enter the %Complete for each individual task, then the
Summary and
Project %Complete will be calculated for you, you have no control
over
this
and cannot fudge the summary figures without fudging the task's
data. If
that's not happening, tell us what is happening, how/where you
enter
the
data and what you are expecting to see.

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for Project Tutorials

wrote:
wow...this is precisely why I wanted to take this off-line, so
I
could
hopefully avoid you John. Your sanctimonious reply is not in
the
least bit helpful, but only rubs salt in an already painful
wound.
First of all...I have just inherited this project and you have
no
clue how I, my company, or the customer have arrived at this
point.
So please refrain from the judgements and ciriticisms. If you
don't
want to help then don't. The schedule needs to be there and I
would
like to show % complete based on what I am being told by the
experts
is the percentage complete on the individual tasks. I would
like
the
real% complete to be reflected in the summary tasks and the
project
summary. If someone knows how I can do this I would appreciate
the
tip so I can just make it through the end of this project and
then
I
can start the right way with the next.

Hoping for a helpful response!

mareveli

:


Help! Is there someone who will take pity on me and give me
an
email address so I don't have to bother this community with
my
stupid questions? Here's the deal...I've had to throw this
schedule together really fast without time to bone up on
msproject.
I loaded the resources incorrectly, a lot of the durations
are
bogus because we wanted certain end dates to show. I just
need
to
be able to show accurate progress but really can't figure out
which
approach is best for this when the data being used is not
accurate.
I am taking a class, but not until next week and I really
need
to
 
J

John

Mareveli said:
It sounds like you are telling me that it can be done through a "custom
parameter" and that it can be defined in Project. Can you point me in the
right direction for how to do this?

Thank you and by the way...I apologize for my earlier response. I was
beyond stressed, but that was no excuse for such harshness.

Mareveli

Mareveli,
Apology accepted. I think I was just the first person to read your
desperate plea for help on what must have been a frustrating weekend at
the office. Since there wasn't an actual question I responded with some
basic truths based on my interpretation of what you wrote. My response
was "harsh" so it's no wonder your reaction to it was also. Nonetheless,
no harm done. Let's see if we can help get you going or at least help
you understand, now that the pressure on you seems to have let up.

By the way, I recall you were going to take a class or get some training
on Project. How is that going? Understanding the principles of project
management and how Project works in that environment are essential for
understanding my, (or other MVPs), responses to your questions.

OK, back to the current question. This may sound like we just keep
hitting the same nail but it is relevant to the issue. Defining custom
fields for progress depends on what form of progress is of interest. If
it is strictly based on the passage of time, then progress is measured
in terms of durations and % complete. If it is effort based, then
progress is measured in terms of work and % work complete. The latter is
generally the accepted approach because effort gets things done, passage
of time does not.

Now some specifics. As I mentioned timescaled values already exist for
several parameters that track progress (e.g. work, actual work, %
complete, cumulative % complete, etc.). There is also a field that shows
timescaled work as originally planned - Baseline Work. However what does
not exist are timescaled values for baseline duration, those would have
to be calculated. In order to show some type of, "where we are at some
point in time", versus, "where we should be at that point in time", a
summation of timescaled values up to that point in time are needed.

In Project there are two ways to get customized values. For static data,
(i.e. non-timescaled), formulas in custom fields will usually suffice.
For timescaled data and more complex calculations, VBA is required.
Either way, calculated values can be put into spare fields in Project or
can be exported to other applications (e.g. Excel). For example, I
worked for a company that used accounting month calendars. Since Project
does not support accounting month calendars, the existing Project data
had to be manipulated and presented in terms of accounting months. I
used VBA with a customized algorithm to convert the data and then
exported it to Excel for presentation.

Hopefully I haven't confused or frustrated you even more. The bottom
line is, you can do virtually anything you want to do, but getting there
requires a clear definition of the requirements.

John
Project MVP
John said:
Mareveli said:
I don't necessarily need to see this in msproject. If I can import the
data
into excel and view it there, that would be great. I'm surprised that
there
isn't a way to see weekly progress, it seems like a very reasonable way
to
monitor progress. Even a weekly view of work planned vs actual work in
excel
would help.

Mareveli

Mareveli,
As you found out from Steve's response, Project has three different ways
of measuring progress. One is based on duration, one is based on effort
(work) and the third is more-or-less user defined. Given that, as Rob
indicated in his response, it depends on how you define the various
progress parameters you listed (i.e. weekly plan %, weekly actual %,
etc.).

In the Project Management world, "progress" is measured using earned
value metrics, rather than basing everything on simple percent complete.
That's why you don't see fields in Project that relate directly to the
progress parameters you listed. If you are not familiar with earned
value, it basically measures progress by comparing cost and schedule to
a baseline. Earned value is computed in terms of dollars (or whatever
the local monetary type).

You can see the weekly percent complete (duration based) on the Task
Usage view if the timescale is set for weeks. And the cumulative actual
percent complete (again duration based) is the % Complete field itself.
However, no such parameter exists for weekly plan % complete, weekly
delta % complete, or cumulative plan % complete.

So, whether the custom parameters are calculated in Project or export to
another application, the exact formula needs to be defined.

Hope this helps.
John
Project MVP
:

Project doesn't compute those values (weekly numbers). You should
decide the algorithm for making those computations, assign the results
of those computations to custom number fields, display those fields on
the screen then print the screen.

Mareveli wrote:
Thanks for staying with me....I do get the difference between the
three.

Another question..maybe I'm supposed to start another thread???

What is the best way to create a weekly report which shows:
weekly plan%, weekly actual%, weekly delta%, cumul. plan%, cum
actual% &
cum
delta%?

Thanks,
Mareveli

:

Project has three completion metrics available. % Complete refers
to
available working time elapsed so far versus total project duration.
%
Work
Complete is the number of man-hours spent versus the total man-hours
required. And finally, % Physical Complete is an estimate of the
amount
of
deliverable completed versus the amount required (often a very
tricky
thing
to quantify - what objectively measurable attribute would the
statement
"The
computer program I'm writing is 65% Physical Complete" be referring
to?)
--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs


Thanks Steve...I think I'm there. I've done all that now. What is
concerning me is that based on our billing and progress kept by the
engineering manager (who was doing all this through excel before
the
customer
demanded msproject) the progress is not quite 70%. The %complete I
am
showing in msproject is 91%. I took all the data for the msproject
schedule
from the eng mgrs spreadsheets. The % work complete is showing at
79%.
It
seems that this is a much better calculation to show progress than
%
complete. It's closer, but still off.

Mareveli

:

Sometimes a viable approach is to build the complete plan as if
work
had
not
yet taken place using the durations that the tasks that are
complete
actually took and the duration estimates for the tasks that are
still
to
be
worked. Then switch to the tracking table and tracking Gantt
views,
mark
the completed tasks as done and where necessary update the Actual
Start
and
Actual Finish dates for them, then enter Actual Start dates and
Actual
and
updated Remaining durations (if necessary) for tasks that are in
progress.
--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs


Thanks for all of the responses. I finally have some breathing
space
since I
don't have any deadlines for the next few days (I hope), so I
should
be
able
to take the time now to obtain accurate dates and durations. If
not,
I'll
try Julie's suggestion.

Thanks again for the input!

Mareveli

:

One more suggestion - am not sure how useful it is though. Why
not
use
Excel spreadsheet instead of MS Project - since most of the
tasks
are
complete. This spreadsheet could have the required columns and
then
they can be filled out. Looking at the situation, am not too
sure
whether putting everything together in MS Project is the way to
go -
it
looks like there will be too much of effort without
corresponding
benefits.

HTH.


Steve House wrote:
Why can't you use the tracking tools that Project provides?
Just
remember
that "% Complete" refers to duration, not work performed and
not
the
amount
of the deliverable that has been done. If a task has 5 days
duration
and
has been worked on for 3 days with 2 still to go, the task is
60%
Complete.
If you have a task showing it starts such and such a date and a
certain
duration and enter a number for % Complete, Project will assume
it
began on
the date the schedule shows and your input percentage of the
total
duration
has been consumed doing the task so far. Or regardless on the
estimated
start date your schedule called for and the duration it shows,
if
you
display the Tracking Table in the Gantt chart view and enter
the
date
the
task actually began in the Actual Start field, the amount of
time
that
work
occupied so far in the Actual Duration column, and the
resource's
best
guess
as to the amount of time remaining until the task is finished
in
the
Remaining Duration, Project will update the duration and
display
the
correct
% Complete for you. And it will rollup those values to the
summary
task
lines and the Project Summary task as well, displaying there a
weighted
average progress based on the actual progress posted for the
activities.
Project IS showing you the real % complete in the summary lines
-
why
do you
think it's not?

--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs


message
Well, maybe at this point I should just create a notes column,
input
the
%s,
and title it "% complete." It is accurate data. The only
problem
with
this
is that I am already using the notes column for notes.

mareveli

:

Hi Mareveli ,

I think John gave you a realistic and honest answer to your
situation. :)

If you enter the %Complete for each individual task, then the
Summary and
Project %Complete will be calculated for you, you have no
control
over
this
and cannot fudge the summary figures without fudging the
task's
data. If
that's not happening, tell us what is happening, how/where
you
enter
the
data and what you are expecting to see.

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for Project Tutorials

wrote:
wow...this is precisely why I wanted to take this off-line,
so
I
could
hopefully avoid you John. Your sanctimonious reply is not
in
the
least bit helpful, but only rubs salt in an already painful
wound.
First of all...I have just inherited this project and you
have
no
clue how I, my company, or the customer have arrived at this
point.
So please refrain from the judgements and ciriticisms. If
you
don't
want to help then don't. The schedule needs to be there and
I
would
like to show % complete based on what I am being told by the
experts
is the percentage complete on the individual tasks. I would
like
the
real% complete to be reflected in the summary tasks and the
project
summary. If someone knows how I can do this I would
appreciate
the
tip so I can just make it through the end of this project
and
then
I
can start the right way with the next.

Hoping for a helpful response!

mareveli

:


Help! Is there someone who will take pity on me and give
me
an
email address so I don't have to bother this community
with
my
stupid questions? Here's the deal...I've had to throw
this
schedule together really fast without time to bone up on
msproject.
I loaded the resources incorrectly, a lot of the durations
are
bogus because we wanted certain end dates to show. I just
need
to
be able to show accurate progress but really can't figure
out
which
approach is best for this when the data being used is not
accurate.
I am taking a class, but not until next week and I really
need
to
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top