B
btrippindacap
In 2003 you could select a task and select hide it from your view. In
2007 they don't have this feature. Does anyone have a work around for
this? The only setting I have seen is under the server settings in
which you can change the number of days forward and back to show
overdue, completed and yet to be done task assignments. This seems
like a step backward in 07. Can't I simply change the view to filter
out those items? If so, where is that set. The manage views under
server settings is a vastly stripped down version of WSS view editing.
thanks,
n8
2007 they don't have this feature. Does anyone have a work around for
this? The only setting I have seen is under the server settings in
which you can change the number of days forward and back to show
overdue, completed and yet to be done task assignments. This seems
like a step backward in 07. Can't I simply change the view to filter
out those items? If so, where is that set. The manage views under
server settings is a vastly stripped down version of WSS view editing.
thanks,
n8