Hide multiple tasks simultaneoustly in PWA-2003

N

Normand

Bonjour,

We have many completed tasks in PWA-2003, Task View.
We want to hide them simultneously.
How can we hide multiple completed tasks simultaneously from the Task View ?

merci !
 
R

Reid McTaggart

First, you can only hide one task at a time with the Hide button.

One thing that will cut down on the clutter is to select the Current Tasks
view from the pane on the left side of the Task view. Current tasks are only
those tasks that are incomplete or which are scheduled within the time window
that is specified in the PWA configurations.

If a resource's work on an entire project is finished, the the PM can make
the assignments for that resource on that project disappear from the
timesheet by changing the resource's booking type from Committed to Proposed
and then republishing the assignments.
 
K

Kevin W Flanagan

You can run a SQL query to hide all tasks in the users timesheets at once.
 