Management would like to use Project Server for tracking actual staff costs
against projects. However they are only prepared to allow Resource Managers
see this information for their direct reports.
Ideally it would be possible to set permissions to hide and lock the cost
fields in the Ent Res Pool and schedules, but on reading other posts this
does not seem possible. Instead it looks like I am going to have to set the
costs at $1/hr and export the plan to excel and apply multiplying factors
there to see progress vs actual.
Has anyone come up with a better way?
against projects. However they are only prepared to allow Resource Managers
see this information for their direct reports.
Ideally it would be possible to set permissions to hide and lock the cost
fields in the Ent Res Pool and schedules, but on reading other posts this
does not seem possible. Instead it looks like I am going to have to set the
costs at $1/hr and export the plan to excel and apply multiplying factors
there to see progress vs actual.
Has anyone come up with a better way?