K
Katie B
Hi Dale,
Thanks for your response to the question that I posted in the
pro_and_server newsgroup regarding the Manage Organization and Hide
Button functionality. I followed the directions to enable the "Hide
Task from Timesheet" that you suggested below and in fact, it has been
enabled/the Allow button has always been checked, yet our resources are
not able to see the Hide button on their timesheet. We can see the
Reject button, but not the Hide button. I tried unchecking the Allow
button and leaving both the Allow and Deny buttons unchecked, and
Saving and I was able to see the Hide button in the Tasks section
logged on as the Admin. When I logged off though and logged back on as
a Team Member to my individual timesheet, the button was not visible,
as it was when logged in as the Admin.
Any further suggestions?
Your original response:
"
Katie --
In the future, please post your Project Server questions to the
microsoft.public.project.server newsgroup, as this newsgroup is going
to
close down. To answer your question, complete the following steps:
1. Log into PWA with administrator permissions
2. Click Admin - Server configuration
3. In the features grid, scroll to the Tasks section
4. Set the Hide Task from Timesheet permission to Allow
5. Click the Save Changes button
Hope this helps.
"
Thanks!
Katie Begell
Thanks for your response to the question that I posted in the
pro_and_server newsgroup regarding the Manage Organization and Hide
Button functionality. I followed the directions to enable the "Hide
Task from Timesheet" that you suggested below and in fact, it has been
enabled/the Allow button has always been checked, yet our resources are
not able to see the Hide button on their timesheet. We can see the
Reject button, but not the Hide button. I tried unchecking the Allow
button and leaving both the Allow and Deny buttons unchecked, and
Saving and I was able to see the Hide button in the Tasks section
logged on as the Admin. When I logged off though and logged back on as
a Team Member to my individual timesheet, the button was not visible,
as it was when logged in as the Admin.
Any further suggestions?
Your original response:
"
Katie --
In the future, please post your Project Server questions to the
microsoft.public.project.server newsgroup, as this newsgroup is going
to
close down. To answer your question, complete the following steps:
1. Log into PWA with administrator permissions
2. Click Admin - Server configuration
3. In the features grid, scroll to the Tasks section
4. Set the Hide Task from Timesheet permission to Allow
5. Click the Save Changes button
Hope this helps.
"
Thanks!
Katie Begell