Hide Tasks in Timesheet Functionality

K

Katie B

Hi Dale,

Thanks for your response to the question that I posted in the
pro_and_server newsgroup regarding the Manage Organization and Hide
Button functionality. I followed the directions to enable the "Hide
Task from Timesheet" that you suggested below and in fact, it has been
enabled/the Allow button has always been checked, yet our resources are
not able to see the Hide button on their timesheet. We can see the
Reject button, but not the Hide button. I tried unchecking the Allow
button and leaving both the Allow and Deny buttons unchecked, and
Saving and I was able to see the Hide button in the Tasks section
logged on as the Admin. When I logged off though and logged back on as
a Team Member to my individual timesheet, the button was not visible,
as it was when logged in as the Admin.

Any further suggestions?

Your original response:
"
Katie --

In the future, please post your Project Server questions to the
microsoft.public.project.server newsgroup, as this newsgroup is going
to
close down. To answer your question, complete the following steps:


1. Log into PWA with administrator permissions
2. Click Admin - Server configuration
3. In the features grid, scroll to the Tasks section
4. Set the Hide Task from Timesheet permission to Allow
5. Click the Save Changes button


Hope this helps.



"

Thanks!
Katie Begell
 
R

Reid McTaggart

Somewhere, in either a Group or in individuals' global permissions, the Hide
Task from Timesheet permission is denied.
 
K

Katie B

Reid, you're a genius! That was exactly the problem and I had
completely overlooked the Manage Users and Groups Admin function.

Thanks so much for making my people so much happier!!!

Katie
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top