Mark Byington
We've had people hide tasks in their 'View my Tasks' task sheet view that had
hours posted to them.
Unfortunately, when an admin or manager goes into the 'View Resource
Assignments' view for that same resource, those same tasks are still 'hidden'
and there doesn't seem to be a way to know that unless you compare it to the
Proj Pro schedule using the resource usage view.
With mgrs trying to report actual hours over the last quarter, say, if they
take the PWA View to generate their report, they may be under reporting time
logged.
While it's obviously this is a training issue for team members and is being
addressed, is their anything else that can be done. It seems to me that
hidden tasks on the time sheet should NOT be hidden in the 'view resource
assignments'. Does MS consider this an issue?
THanks,
hours posted to them.
Unfortunately, when an admin or manager goes into the 'View Resource
Assignments' view for that same resource, those same tasks are still 'hidden'
and there doesn't seem to be a way to know that unless you compare it to the
Proj Pro schedule using the resource usage view.
With mgrs trying to report actual hours over the last quarter, say, if they
take the PWA View to generate their report, they may be under reporting time
logged.
While it's obviously this is a training issue for team members and is being
addressed, is their anything else that can be done. It seems to me that
hidden tasks on the time sheet should NOT be hidden in the 'view resource
assignments'. Does MS consider this an issue?