Hiding milestone tasks in Resource Usage View

D

Deluth

I have a Resource Pool that I've shared across multiple projects. I keep getting all the "unassigned" tasks in the Resource Pool - these, of course are the milestones that are showing up as unassigned. How do I hide them from the Resource Usage view? They're not real tasks anyways - they're milestones, right?
 
J

Jan De Messemaeker

Hi,

There must be several ways to hide the unassigned assignments:

- Simply click the little minus sign in front of "Unassigned"
- Or use the filter "Resource range" with a range betwen 1 and, f.i. 1000

HTH

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/index.htm
32-495-300 620
Deluth said:
I have a Resource Pool that I've shared across multiple projects. I keep
getting all the "unassigned" tasks in the Resource Pool - these, of course
are the milestones that are showing up as unassigned. How do I hide them
from the Resource Usage view? They're not real tasks anyways - they're
milestones, right?
 