Hiding Tasks that are 100% complete

M

MK

Can you tell me how to hide tasks that show 100% complete please?
I have some old ones assigned to me but are 100% complete and they still
show up.
It makes it very difficult for me to find the tasks I actually need to log
my time against when I have so many of these old ones still showing up…
 
B

bikerjohn

I am assuming that you are talking about the my tasks view in pwa. If so,
there are a few things you can do to help but no real magic bulltet. 1: you
can see if your admin will change the setting for current tasks. If so, this
will prevent older tasks from displaying. Outside of that, the only other
thing you can do from within the my tasks area, go to the tasks gantt view
and create a filter to filter out tasks with 0 remaining work or tasks that
are 100% complete.
 
M

MK

Thank you I was able to create the filter as you advised below, however I am
not able to get that filter to apply to my “My Tasks†page.
Is there some way to get it to apply to the “My Tasks†page? This is the
page that takes forever for me to use because I have to scroll through so
much old stuff.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.