T
TheDrake
Hi
I am new to MS Project and have not used Project Management software
previously.
I need to show on the Gantt chart when a subsequent task should start in
relation to its predecessors.
Example - when TASK 4 is 25% complete then TASK 7 and TASK 39 must begin.
Of course the lower down the list a task appears the less obvious is the
link to a much higher up task.
We therefore need a visual (Vertical) line to show up from those tasks to
indicate that dependance and also to highlight this.
I have seen this feature on reports from other software and need to know if
this is possible in MS Project Professional.
Many Thanks
I am new to MS Project and have not used Project Management software
previously.
I need to show on the Gantt chart when a subsequent task should start in
relation to its predecessors.
Example - when TASK 4 is 25% complete then TASK 7 and TASK 39 must begin.
Of course the lower down the list a task appears the less obvious is the
link to a much higher up task.
We therefore need a visual (Vertical) line to show up from those tasks to
indicate that dependance and also to highlight this.
I have seen this feature on reports from other software and need to know if
this is possible in MS Project Professional.
Many Thanks