T
The nugget
Hi
I've worked my way through 2 manuals, but I still can not work out how to
simply run a report against a gant chart that shows tasks which should have
finished by a date in the past and have not been completed or are due to
finish by a date in the future and are not complete- I want to do aweekly
report which shows, incomplete tasks for that week and those that are due for
completiogn that wee. The report would be run for example on a Modnay
mornign would show things that are outstanding for the previosu week (and
further if needed) and show tasks that are due to be completed this week.
At present I do this maually.
Thanks in advance
Andy
I've worked my way through 2 manuals, but I still can not work out how to
simply run a report against a gant chart that shows tasks which should have
finished by a date in the past and have not been completed or are due to
finish by a date in the future and are not complete- I want to do aweekly
report which shows, incomplete tasks for that week and those that are due for
completiogn that wee. The report would be run for example on a Modnay
mornign would show things that are outstanding for the previosu week (and
further if needed) and show tasks that are due to be completed this week.
At present I do this maually.
Thanks in advance
Andy