Paul Mattaliano
Is there a way to highlight tasks that have gone past the
finish date. I have tried saving a baseline then Filter -
-> More Filters --> Slipped/Late Progress and clicked
Highlight but I don't see any changes in my plan and am
not sure what to edit.