S
sK
I am managing a very lengthy schedule. I recently went through to weed out
all tasks that were 100% complete. For those completed tasks that had
incomplete successors, I moved them to a section called completed tasks and
restablished the links.
Now when I filter for critical tasks and try to highlight them, nothing is
highlighted, whereas before I was able to highlight the critical path. Can
anyone tell me why that might be. We are wondering if the Completed tasks
section would affect this?
all tasks that were 100% complete. For those completed tasks that had
incomplete successors, I moved them to a section called completed tasks and
restablished the links.
Now when I filter for critical tasks and try to highlight them, nothing is
highlighted, whereas before I was able to highlight the critical path. Can
anyone tell me why that might be. We are wondering if the Completed tasks
section would affect this?