S
smudge20
I am quite new to Project (was more involved with P3/P3e). The project I am
on at present will be having a shutdown for a week, twice in the year. In P3
it is easy to highlight the area required by using a "curtain". I have
sussed that you can do it in Project as well, by using the drawing toolbar,
but the default is only for 40cm. I have a Project with almost 4000
activities on it and I want to highlight the whole plan to show the shutdown
period. Is there a work around to this. I tried changing the working time
colours, but it doesn't seem to offer you the change possibility.
Can anyone help?
on at present will be having a shutdown for a week, twice in the year. In P3
it is easy to highlight the area required by using a "curtain". I have
sussed that you can do it in Project as well, by using the drawing toolbar,
but the default is only for 40cm. I have a Project with almost 4000
activities on it and I want to highlight the whole plan to show the shutdown
period. Is there a work around to this. I tried changing the working time
colours, but it doesn't seem to offer you the change possibility.
Can anyone help?