highliting weekends and hollidays in PWA

F

Frank

Hello,

we are using Project Web Access for time reporting - but
it gets quite disturbing since you can't tell weekdays and
workdays from weekends and hollidays in the PWA "task"
page - thus our question:

"is there a way to highlite weekends and hollidays - or
make it impossible to enter hours there in PWA
timesheets???"

thank you for your help

Frank
 
F

Frank

Internally we have to stick to the half month periods - is
there any other possibility??? maybe changing the code???

thanks for your help

Frank
 
G

Gary L. Chefetz \(MVP\)

Frank:

You need to judge this for yourself. There's extensive information on the
customizability of the EPM environment on MSDN. You sure you can't overcome
this with some training?

--

Gary L. Chefetz, MVP
"We wrote the book on Project Server
http://www.msprojectexperts.com

-
 
F

Frank

well - training might be an option - it just seems so easy
if thouse fields where colored or even blocked - it would
make the PWA Task view much better since it would be
easier to report time if you can see the weekends -
training can't account for a good simple setup...

well - i will see...

thanks

Frank
 