I have done this and have used no code.
you just need to setup rules for this..
Mine is sending a attached mail to the manager and submitting it to
sharepoint with one go. When the manager approve the holiday it again
get mailed to the user and to sharepoint where my calender is shown.
My only problem I got now is that my end date is not taken in account
on the Calender. this is because info path puts in a time of 00:00.
Even if the user only specify the date. If any one have any Idea how
to fix this or change the time but not the date in the code please can
you let me know.
I am happy to send my form on for you to have a look if need be.
Thanks
I have done this and have used no code.
you just need to setup rules for this..
Mine is sending a attached mail to the manager and submitting it to
sharepoint with one go. When the manager approve the holiday it again
get mailed to the user and to sharepoint where my calender is shown.
My only problem I got now is that my end date is not taken in account
on the Calender. this is because info path puts in a time of 00:00.
Even if the user only specify the date. If any one have any Idea how
to fix this or change the time but not the date in the code please can
you let me know.