If a holiday falls at a weekend, does MSP 2007 automatically schedule the non
working day for the following working day or does this have to be inputted
manually?
For example, I am trying to set New Years day as a non working day for a
project spanning 2009-2012. 1 Jan 2010 falls on a Friday, but then 1 Jan 2011
falls on a Saturday and 2012 on a Sunday.
Instead of setting an exception with a yearly recurrence pattern, should
each New Year holiday be entered separately? For example entering New Year
2011 as Monday 3rd January instead of 1st as this is the first working day
after Saturday 1st?
I am new to MSP so any help would be very much appreciated.
Thank you
working day for the following working day or does this have to be inputted
manually?
For example, I am trying to set New Years day as a non working day for a
project spanning 2009-2012. 1 Jan 2010 falls on a Friday, but then 1 Jan 2011
falls on a Saturday and 2012 on a Sunday.
Instead of setting an exception with a yearly recurrence pattern, should
each New Year holiday be entered separately? For example entering New Year
2011 as Monday 3rd January instead of 1st as this is the first working day
after Saturday 1st?
I am new to MSP so any help would be very much appreciated.
Thank you