Hourly and daily rates - confusion

H

Hans Wurst

Hi there,

I don't know whether I got a little problem:

Ressource costs are:
- 100 € / hour or
- 800 € / day considerd a 8 hour-day.

If a hour-ressource enters now 8 hours I want project to show actual costs
of 800 €.

If a day-ressource enters 6 hours I want project to show actual costs of 800
€ - the same if the ressource enters 10 hours.

But project calculates always on a hour-base.

Can I change that somehow?

Best regards

Michael
 
G

Gary L. Chefetz [MVP]

Hans,

You'll need to write some code to calculate cost based on FTE days. This is
not a functionality baked into Project Server.
 