Hi there,
I don't know whether I got a little problem:
Ressource costs are:
- 100 € / hour or
- 800 € / day considerd a 8 hour-day.
If a hour-ressource enters now 8 hours I want project to show actual costs
of 800 €.
If a day-ressource enters 6 hours I want project to show actual costs of 800
€ - the same if the ressource enters 10 hours.
But project calculates always on a hour-base.
Can I change that somehow?
Best regards
Michael
I don't know whether I got a little problem:
Ressource costs are:
- 100 € / hour or
- 800 € / day considerd a 8 hour-day.
If a hour-ressource enters now 8 hours I want project to show actual costs
of 800 €.
If a day-ressource enters 6 hours I want project to show actual costs of 800
€ - the same if the ressource enters 10 hours.
But project calculates always on a hour-base.
Can I change that somehow?
Best regards
Michael