S
Shane
Hello Project experts
I am invovled in a Project course right now, but have an more immediate need
I work for a consulting firm, and here is the situation
When we do a project, we want to know the duration in calendar days, but the effort in terms of hours so we can develop a budget based on our hourly fees. For example, we know a task could take 4 hours to do, but because we have to work on other client work at the same time, the task won't be complete for 2 calendar days
How do we reflect that in Project?
Thanks!
I am invovled in a Project course right now, but have an more immediate need
I work for a consulting firm, and here is the situation
When we do a project, we want to know the duration in calendar days, but the effort in terms of hours so we can develop a budget based on our hourly fees. For example, we know a task could take 4 hours to do, but because we have to work on other client work at the same time, the task won't be complete for 2 calendar days
How do we reflect that in Project?
Thanks!