I'm planning a one-day event that will take place in multiple locations with
multiple performers. I would like to use Project to keep track of all this
schedule using a Gannt chart to show the start/finish time for each performer
in each location. I can't seem to figure out how to enter the start
time/finish time in an hourly format and to get the duration to display in
hours vs. days. I can get the Gantt chart to appear in 24-hour format, but
if I can't get the data in an hourly fashion, then that's not all that useful
 
J

JulieS

Hello Project123,

To display the Start/Finish times: Tools > Options, view tab. Change the
default date format to one showing time.

While in Tools > Options, click the Schedule tab and change "Duration is
entere in:" to Hours.

I hope this helps. Let us know how you get along.

Julie
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top