B
BobA
I've a enterprise level project where I need to be able to report the days
expected to complete a task AND the total hours required.
Since there are multiple dependancies with almost all tasks, it is necessary
to schedule and track hours and days.
For example, if task "A" is slotted to take Bill 8 hours, but it will be
spread across 3 days - how can I assign that task as 8 hours but still
schedule it to reflect over a 3 day period.
I'd like to insert a new 'time' column that would track to the resource, but
not affect the duration shown.
Thanks in advance
expected to complete a task AND the total hours required.
Since there are multiple dependancies with almost all tasks, it is necessary
to schedule and track hours and days.
For example, if task "A" is slotted to take Bill 8 hours, but it will be
spread across 3 days - how can I assign that task as 8 hours but still
schedule it to reflect over a 3 day period.
I'd like to insert a new 'time' column that would track to the resource, but
not affect the duration shown.
Thanks in advance