K
Katie B
Good Afternoon,
We've come across this issue multiple times where Actual Work hours are
appearing for certain individuals in MS Project, but when you check
their timesheet in PWA, the hours do not appear for that task. Our
standard procedure is to make any adjustments to Actual Work hours in
PWA and then update/commit the changes to MS Project Professional, not
vice versa, but when the hours aren't appearing in PWA, there's no
adjustment that can be made. And if I try to zero out the hours in MS
Project, when I save, it asks me if I want to synch with protected
actuals and then it adds the hours back in that I deleted.
Any suggestions? Please let me know if you need more information.
Thanks!
Katie Begell
We've come across this issue multiple times where Actual Work hours are
appearing for certain individuals in MS Project, but when you check
their timesheet in PWA, the hours do not appear for that task. Our
standard procedure is to make any adjustments to Actual Work hours in
PWA and then update/commit the changes to MS Project Professional, not
vice versa, but when the hours aren't appearing in PWA, there's no
adjustment that can be made. And if I try to zero out the hours in MS
Project, when I save, it asks me if I want to synch with protected
actuals and then it adds the hours back in that I deleted.
Any suggestions? Please let me know if you need more information.
Thanks!
Katie Begell