hours assigned varies in Timesheet

G

Girija

Hello,

A resource has been assigned 10 hrs for a task. He wants to update in PWA.
In timesheet as he enters, the duartion changes in the task assignment
window. Is it because he might be entering more number of hours (more than 10
hrs) than mentioned?

Thanks

Girija
 
D

Dale Howard [MVP]

Girija --

Yes, that is certainly possible. If you assign a resource to work 10 hours
over 2 days, for example, but on the My Timesheet page he/she enters 5 hours
per day for 4 days, the new Duration is 4 days and not 2 days. And the
total Work is now 20 hours, which is 10 hours over the original budget of 10
hours. Thus, you have 10 hours of Work Variance and 2 days of Duration
Variance on the task. Hope this helps.
 
P

/pd

Dale

correct me if I am wrong here.. timesheet data DOES NOT update the project
plan. So I am unsure how the project will reflect TotalWork = 20Hr ,
WorkVariance=10H and SchVariance = 2D ?

Unless...

The resource updates the assinged Task to reflect the 5hrs pers day across
4d, then the prjplan would reflect what you varanice...correct ??
 
D

Dale Howard [MVP]

/pd --

I'm assuming the team member enters the time in his/her My Timesheet page
and then imports the time into his/her My Tasks page, and then submits the
task update to the PM for approval. Once approved, the variances are as I
indicate. Hope this helps.
 
P

/pd

Dale

Yes now that makes sense. I missed out that scenario. Import Timesheet into
tasks

thanks for the headsup.. another scenario that I must test out as a workflow
for the resource team.. :)-

/pd
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top