hours/day in PWA and in Project Pro 2002

  • Thread starter Muriel Fournier
  • Start date
M

Muriel Fournier

Hello,
I'm working on the French version of Project server 2002.
A resource created a task in PWA, with a work load of 6 days. PWA interpret
this load as 48h.
The Duration of the task is 6 days in PWA.

The French version of Project 2002 is provided by Microsoft with a 35h/week
calendar.
So in Project Pro the Duration of this same task is 6.86 days.

How can I correct this heterogeneity between PWA and Project?

Thanks for help,

Muriel
 