Environment: Project 2007 SP1, patched up to and including the February CU.
Scenario:
We have a task that is assigned to a resource at 100%. That resource has a
9 hour resource calendar assigned. When that resource records his time on
PWA, diligently entering 9 hours/day, the hours are not coming through
correctly on the project plan. We get 8.1 hours actuals on the days where 9
hours were recorded, and the balance of the time is recorded on the next
available day. The task is a Fixed Duration task with a SNET constraint, and
this is working fine for people with other calendars. In fact, it’s also
working fine when trying to reproduce this on another plan, with the same
parameters.
Any ideas on how to fix this without having to rebuild the plan would be
gratefully received.
Scenario:
We have a task that is assigned to a resource at 100%. That resource has a
9 hour resource calendar assigned. When that resource records his time on
PWA, diligently entering 9 hours/day, the hours are not coming through
correctly on the project plan. We get 8.1 hours actuals on the days where 9
hours were recorded, and the balance of the time is recorded on the next
available day. The task is a Fixed Duration task with a SNET constraint, and
this is working fine for people with other calendars. In fact, it’s also
working fine when trying to reproduce this on another plan, with the same
parameters.
Any ideas on how to fix this without having to rebuild the plan would be
gratefully received.