J
James from Sage
I'm using EPM Server 2003 with SP2.
I find the some of actual updated hours (as shown in black) in the Update
Actuals view are different than what I saw when I open a file in MS project
and use the Resource Usage view and select both Work and Actuals for the
right side - even though the same tasks are visible.
Thanks,
- James
I find the some of actual updated hours (as shown in black) in the Update
Actuals view are different than what I saw when I open a file in MS project
and use the Resource Usage view and select both Work and Actuals for the
right side - even though the same tasks are visible.
Thanks,
- James