Hours per resource for rolled tasks

J

Judy

Is there anyway to display the total hours assigned to each resource for a
rolled up task?
 
J

Jim Aksel

Try using either the Task Usage or Resource Usage Views available under the
View menu. I believe you will find the Task Usage View to your liking.
*****
If this post was helpful, please consider rating it.

Jim Aksel, MVP

Check out my blog for more information:
http://www.msprojectblog.com
 
J

JulieS

Hi Judy,

I am guessing that you mean summary tasks when you say "rolled up
task". You might try experimenting with grouping in the Task Usage
view to see if that gets you close. For example, a group with the
definition:

Group by:
Field: Outline Number
Field Type: Task
Order: Ascending

Then by
Field: Name
Field Type: Task
Order: Ascending

Then By
Field: Resource Names
Field Type: Assignment
Order: Ascending

Would show for each summary task, the task name and then the
resources assigned. If you add the work field to the view, you can
see total work per summary task, total work per task under the
summary and the totals per resource per task.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
 