M
Michelle Hotz
We are on PS2007, SP1, IU, Dec cummulative updates.
Since applying IU update and Dec cummulative updates a few weeks ago, we are
noticing that some resources have hours pre populated on timesheet with
planned hours, while others do not.
We don't want this happening, and it wasn't happening before. We also added
a web part to hide Planned Hours on timesheets.
Any thoughts on why this might be happening?
Thanks,
Michelle
Since applying IU update and Dec cummulative updates a few weeks ago, we are
noticing that some resources have hours pre populated on timesheet with
planned hours, while others do not.
We don't want this happening, and it wasn't happening before. We also added
a web part to hide Planned Hours on timesheets.
Any thoughts on why this might be happening?
Thanks,
Michelle