Keith
Hi,
I have a 2003 Project with around 100 tasks. I have the start & finish
dates formatted to show the date and hour. My default start and end times
are (tools, options, calendar) are set to 8:30 AM and 4:30 PM. Hours per day
is set to 7.0. On the standard project calendar my working hours are 8:30 to
12:00 and 1:00 to 4:30.
I have a task that is 35 days long. It is constrained to start on a
specific date which I have entered to be 3/3/08 8:30 AM. At 35 days the
finish column date and time shows 4/18/08 3:30 PM which is wrong. It should
read 4:30 PM. If I lower the duration to 30 days or less, the finish time
shows 4:30 PM. If i increase the duration above 30 days, the finish time
shows 3:30 PM.
Can anyone tell me how to fix this? I must have something set wrong but I
can't figure out what.
Thanks
Keith
I have a 2003 Project with around 100 tasks. I have the start & finish
dates formatted to show the date and hour. My default start and end times
are (tools, options, calendar) are set to 8:30 AM and 4:30 PM. Hours per day
is set to 7.0. On the standard project calendar my working hours are 8:30 to
12:00 and 1:00 to 4:30.
I have a task that is 35 days long. It is constrained to start on a
specific date which I have entered to be 3/3/08 8:30 AM. At 35 days the
finish column date and time shows 4/18/08 3:30 PM which is wrong. It should
read 4:30 PM. If I lower the duration to 30 days or less, the finish time
shows 4:30 PM. If i increase the duration above 30 days, the finish time
shows 3:30 PM.
Can anyone tell me how to fix this? I must have something set wrong but I
can't figure out what.
Thanks
Keith