hours remaining

J

Jason

hello everyone,
If I'm entering "hours" for duration and filling in the "%complete" fields,
is there a way for MSProject to let me know "hours remaining"?

Thank you
 
J

Jason

thank you. and is there a way of showing total remaining hours. The schedule
I've got is pretty long and would be great to show total somewhere.

Thanks again
 
J

Jack Dahlgren MVP

Try the remaining work field.

Not sure if that is what you mean by total hours.

-Jack Dahlgren
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top