How Assign ResA OR ResB

T

Tarvirdi

I have 2 separate worker(resource) and in a task I want to assign both of
them in OR manner. I means that both of them can do job and msp should
select one of them based of availability (W1 or W2, not AND).
How?
MTarvirdi
(e-mail address removed)
 
M

Mike Glen

Hi Tarvirdi ,

Welcome to this Microsoft Project newsgroup :)

Sorry, Project does not have this capability :(

FAQs, companion products and other useful Project information can be seen at
this web address: <http://www.mvps.org/project/>

Hope this helps - please let us know how you get on :))

Mike Glen