I have a project manager who has a project plan uploaded to Project Server
2002, and he wants to be able to schedule tasks around his Enterprise
Resources' schedules.
For his enterprise resources, he wants to be able to input company holidays,
unusual work schedules (not the typical 5 days x 8 hours), vacation days,
sick days, etc.
How can he (or I) do this?
He's told me that "...given that this is an Enterprise Project, my resources
who work for me that are now published can only be changed by someone who has
security permissions", which he doesn't have.
As an Admin, can I modify these resource calendars? (If so, how do I do it?)
Even better, is there some way that he can modify his resources' calendars?
Or can his resources modify their own calendars? (And, if so, how can he/they
do it?)
I'd appreciate your help!
2002, and he wants to be able to schedule tasks around his Enterprise
Resources' schedules.
For his enterprise resources, he wants to be able to input company holidays,
unusual work schedules (not the typical 5 days x 8 hours), vacation days,
sick days, etc.
How can he (or I) do this?
He's told me that "...given that this is an Enterprise Project, my resources
who work for me that are now published can only be changed by someone who has
security permissions", which he doesn't have.
As an Admin, can I modify these resource calendars? (If so, how do I do it?)
Even better, is there some way that he can modify his resources' calendars?
Or can his resources modify their own calendars? (And, if so, how can he/they
do it?)
I'd appreciate your help!