D
Don V
I am using MS Project 2003
I would like to know how I can add a list of materials and tools needed for
a task, and print a report for each task.
We are in a large, high security building. We have 2 rooms for storage for
all of the tools and materials which is about 175 feet apart. Most of the
work being done is about 300 to 400 feet away from the material. Last week we
started this job and I saw a lot of wasted time forgetting materials and
special tools needed for the task.
Can this be done using MS Project 2003?
Below is an example of what kind of report I would like to have.
Example
Task Description: Install 100' 3/4" emt Conduit pipe,
Location : Upstairs Hallway
Persons : Larry, Curly, Moe
Tools needed : Reamer
Drill
2 Ladders
Etc
Materials Needed: 125' 3/4" Emt pipe
2 Sq Emt Box
5 Set srcew male adapters
ECT.
I would like to know how I can add a list of materials and tools needed for
a task, and print a report for each task.
We are in a large, high security building. We have 2 rooms for storage for
all of the tools and materials which is about 175 feet apart. Most of the
work being done is about 300 to 400 feet away from the material. Last week we
started this job and I saw a lot of wasted time forgetting materials and
special tools needed for the task.
Can this be done using MS Project 2003?
Below is an example of what kind of report I would like to have.
Example
Task Description: Install 100' 3/4" emt Conduit pipe,
Location : Upstairs Hallway
Persons : Larry, Curly, Moe
Tools needed : Reamer
Drill
2 Ladders
Etc
Materials Needed: 125' 3/4" Emt pipe
2 Sq Emt Box
5 Set srcew male adapters
ECT.