How can I allocate one resource (i.e Project Supervisor) to two o.

S

satchude

Please I want to know how I can allocate one resource (eg Project Supervisor
to two overlapping tasks
 
E

Earl Lewis

Make sure each allocation doesn't total up to more than the maximum available for the resource. In other words set the Units to a percentage that allows both tasks to be done in the same time without going over your maximum hours per day.

Earl
Please I want to know how I can allocate one resource (eg Project Supervisor
to two overlapping tasks
 