S
Stuart
Hi,
We have recently updated all the resource costs and now of
course it shows up as huge variances, even though the work
effort is still the same.
Is there a way to re-baseline just the resource costs only?
Thanks,
Stuart.
We have recently updated all the resource costs and now of
course it shows up as huge variances, even though the work
effort is still the same.
Is there a way to re-baseline just the resource costs only?
Thanks,
Stuart.