I recently changed the height of a task in an MS Project plan so it would
wrap the task name in a view of a Gantt chart. For some reason, the grey
block to the left of all tasks became clear, and I am no longer able to
select a task to make it regular height again.

Suggestions as to why this might have occurred?

Thanks,
Mike
 
J

Jim Spiller

Either the first column is no longer locked or it is hidden (0 width). Go to
View-Table-More Tables and click Edit to give the first some a width greater
than 0 or Lock it. Click Apply after clicking OK to these changes...
 