Hello, I want to calculate that according the basline plan how much work should be comleted and what is the % complete of baseline work
thanks
 
G

Gérard Ducouret

Hello Reza,
You have to use the Earned Value analysis which has been designed for that.
In the Help, look for BCWS, BCWP, ACWP.

Hope this helps,

Gérard Ducouret [Project MVP]
PragmaSoft ® - Paris