Hello George,
You can add the "Last Saved Date" value to the legend. View the Gantt
chart view and choose File > Page Setup. Click the legend tab. At
the bottom of the dialog are three tabs, Left, Center, and Right. By
default the Project Name and Print date appear on the left tab. To
add the Last Saved Date below, click after the [Date] field and press
enter to place your insertion point below the Date line. In the
drop-down list to the right of "General" find the field "Last Saved
Date". Select it and click the Add button.
Click OK to close the Page Setup dialog, save the Gantt chart and
print.
I hope this helps. Let us know how you get along.
Julie
Project MVP
Visit
http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
George said:
How can I display the last time (date/timestamp) my project was
updated in my
project plan (i.e. the Gantt view)?