A
ad_rav
Hi, Im pretty new to using project. I've got all my info into the time plan,
at the top i have entered all holiday periods so they are clear to see.
When i have tryed to make these non working days they appear in the
calender, but this does not adjust and allow for this time in the plan/gant
chart - eg i want the completion date to finish 2 weeks later because of a
summer shutdown period.
cant find the answer in tutorial... can anyone help please??
at the top i have entered all holiday periods so they are clear to see.
When i have tryed to make these non working days they appear in the
calender, but this does not adjust and allow for this time in the plan/gant
chart - eg i want the completion date to finish 2 weeks later because of a
summer shutdown period.
cant find the answer in tutorial... can anyone help please??