Hi Steve,
Thanks very much for the input, it helps me understand the Project
approach.
My problem still remains, though - I have been asked to use Project to
produce our project plans by a client. we have a tight timeline that
will
no
doubt require us to do a fair amount of overtime. What I would ideally
like
to do is to tell Project when certain tasks must happen and how many
hours
of
work are required by each of our team members to complete each task. I
would
then like Project to respect the timelines and hours, and simply show
me
where I am dramatically in the red in terms of overtime required. I
would
then bring in additional resources or plan to sleep at the office. My
problem is, when I try to do this. Project often overrides my imposed
timelines and dramatically extends them. This gives me a project plan
that I
can't show to my clients, and doesn't give me the overtime reality
check
that I want. Is there really no way for Project to be used this way? I
know
it isn't ideal, but it suits my needs in the short term.
Thanks again,
Jeff
:
Look at it this way. All projects have required dates that must be
met.
But you don't need software to document those requirements - you
already
know what they are. Your problem is figuring out exactly what you
have
to
do to make it happen the way you need it to and that's where the
software
comes in. It's a calculator intended to help you figure out how to
organize
the workflow and to utilize the resources so that those requirements
are
met
by predicting the results you'd obtain IF you go with a given plan of
attack. So you input your tasks, their dependencies, and the resource
assignments you envision and let Project freely calculate the dates
and
suppose it shows your requirements are being missed ... what does that
mean?
What it means is that it has given you a reality check - IF you try to
do
the work according to your first ideas regarding how to organize it,
you're
not going to be successful at meeting your objectives. What can you
do
to
fix it? You can't just somehow force Project to show you the dates
you
want
.... you have to actually materially change the workflow and/or the
resource
assignments in order to make real, physical changes in the forces that
drive
those dates. If you have a building to paint and it's going to take 2
weeks
for the one painter you have to do it yet your client requires it be
delivered in 1 week, you can't just override Project's calculations,
your
only real options are to have your one guy work overtime or to go out
and
hire some more painters so the work goes faster. You can't just
specify
dates out of the blue - you have to do something concrete to make it
happen
that way by changing the real world forces that drive the schedule and
as
you experiment with various workflows, Project will tell you which
ones
will
work and which ones won't. Now to record those required dates in the
schedule is another story - simply entering a deadline on the delivery
milestones will display them and red-flag those that are going over.
HTH
--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit
http://project.mvps.org/faqs.htm for the FAQs
Hi John,
Thanks for the advice, it does sound like the solution long term,
and
thanks
for the tutorial links. Believe me, I have been thinking about
returning
to
Excel! Maybe I should rephrase my question though -
I would like to let project create a dynamic schedule and take
advantage
of
its capabilities. At the same time, I have certain tasks that have
to
occur
on specific dates (required by clients ), and other tasks that have
to
occur
over specific periods of time. How can I tell Project that these
tasks
have
to be limited in this way, and then let it be flexible and dynamic
with
the
rest of the tasks? when I try to do this, Project frequently
changes
the
dates afterwards, leaving me with one-day meetings that are spread
out
over 2
weeks, etc.
Thanks,
Jeff
:
Hi again, and thanks for any help you can give. I want project
to
respect
the dates and the hours of work I assign to a task, even if this
makes
for
herculean efforts on the part of the resources involved; half the
time
that I
assign dates, it ignores them. Is there any solution?
Thanks
Jeff
Jeff,
The title of your post pretty much says it all - you are trying to
make
Project fit your thinking instead of letting it do what it was
designed
to do - that is to create and calculate a dynamic schedule plan
based
on
user inputs of task name, estimated duration, task dependencies,
and
resource assignments. If you insist on setting the dates for tasks
then
you would be much better off using Excel.
I'm sorry to be blunt, but the solution you seek is for you to
learn
how
to create a dynamic working schedule with Project. You do NOT do
that
by
inputting dates. I suggest you take an interactive class on project
management using Project. You could also make use of fellow MVP,
Mike
Glen's tutorials on Project. They can be found on Mike's link at,
http://www.mvps.org/project/links.htm. If you need an excellent
book
on
Microsoft Project, try The Ultimate Learning Guide to Microsoft
Office
Project 2007 from Project Experts. You can find out more at,
http://msprojectexperts.com.
John
Project MVP