How can I Format Work field in PWA

R

rayis

In PWA I am creating a new Project view with Work field in it
The Work always shows in Hours

How can I convert into Days

Does the Work field has any link to the format used in Projec
Professional

Please help
 
R

Reid McTaggart

You can create an enterprise custom field, such as Enterprise Project Number
1, and define it with a formula like [Work] / 8 . Then, add that field to
your view. You'll need to open and save at least one project to get the
field name to show up correctly in PWA, and open/save each project to get all
the values populated in PWA.

-Reid
 