S
Suliman
I print a resource usage report for all resources. I set the date range for a
single work week. If Mike was a resource on 20 tasks but he only worked on 2
tasks during the week that I am printing the report for, how can I get
Project to only list the two resources he actually worked on that week as
opposed to it listing every task he was assigned to. I want those blank tasks
to be hidden when I print.
single work week. If Mike was a resource on 20 tasks but he only worked on 2
tasks during the week that I am printing the report for, how can I get
Project to only list the two resources he actually worked on that week as
opposed to it listing every task he was assigned to. I want those blank tasks
to be hidden when I print.